Why Blackstart Needs a Restoration Chain

A unit can start locally while the wider restoration path remains unavailable.

A generating unit can be capable of starting without the connected grid and still depend on something outside its fence before it can help restore that grid. Fuel must reach it. Other equipment may need electricity. The path to the next generator must be available, and the organizations responsible for the sequence need a workable coordination arrangement.

Counting blackstart-capable units does not describe those dependencies. The more useful object is a restoration path: a set of capabilities and prerequisites that can become available in an executable order.

The December 2023 FERC–NERC–Regional Entity staff study of the Texas Interconnection examined that distinction using information from nine electric and natural-gas entities. It was not a compliance or enforcement initiative. Its definitions, fuel observations and testing discussion provide a dated case, not a current statement of every Texas operating requirement.

Separate the unit from the path

The study distinguishes a blackstart resource from a next-start generating unit reached through a cranking path. A self-starting resource is one part of restoration; energizing the next resource involves a wider electrical and operational arrangement.

The report also describes fuel dependencies that can complicate the apparently simple label “dual fuel.” A unit may be able to run on alternate fuel after starting on primary fuel, without being able to start exclusively on that alternate fuel. Another arrangement may need an external electricity source for part of its startup.

Those are different capabilities. Evidence for running, switching fuels and starting from the required blackout state should not be treated as one interchangeable test result.

The distinction is not an accusation that a particular unit cannot perform its contracted function. Its actual function may be defined under specific conditions and arrangements. The review task is to recover those conditions before extending the capability to a wider restoration claim.

A fictional loop with no first step

Consider an original dependency exercise with invented equipment names. Unit B can start without electricity from the connected grid when its own starter and required fuel are available. Its starter is ready.

Its fuel arrives through facility F. In this exercise, F needs electric power before it can deliver the fuel required by B. The proposed restoration arrangement supplies F from B. No other initial source is available.

Each side of that arrangement can sound reasonable when described separately. B supplies electricity to F; F supplies fuel to B. But beginning with both off, neither can be the first step under the supplied assumptions.

This is a causal loop, not a calculation of insufficient installed megawatts. Increasing B’s output rating does not remove the initial fuel prerequisite. Adding more fuel in a distant supply source does not make the electric-dependent delivery facility operational.

A diagram of the eventual running state may show balanced flows and still conceal the problem. “Both are operating and supporting each other” is a possible description of an established state. It is not evidence that the proposed sequence can reach that state from the stipulated blackout condition.

The exercise is not a model of actual Texas facilities. Its names, prerequisites and initial conditions are invented to show what a dependency map can expose. A real restoration analysis also needs electrical dynamics, equipment limits, procedures and current system evidence that this logical example does not provide.

One way to check this small map is to begin with only the supplied available services. Add an action only when all its prerequisites are already available. Repeat until no further action can be added. With only B’s starter initially ready, neither fuel delivery nor B’s startup can enter the reachable set. Assuming both are on at the end would skip the question the exercise asks.

An independent starting condition changes reachability

Add a fictional independent source X that can supply the required service to F under the evaluated conditions. Stipulate that X is available at the start and that all other requirements for this small path are satisfied.

F can now become available before B. B can then obtain its required fuel and start. The new source has changed the dependency structure: it supplies a prerequisite from outside the original loop.

Apply the same check again. X can first supply F’s electrical requirement; F can then deliver fuel; B’s already-ready starter and newly available fuel allow its startup. This sequence matters because each added action has an earlier justification. Removing X from the initial state removes that justification, even though the drawing of the eventual operating arrangement still looks plausible.

That logical result does not establish the size, duration or physical suitability of a real independent source. Those would need their own evidence. It identifies what role the source must perform rather than selecting equipment by label.

An alternate fuel could change the loop in another way. Suppose B has an independently available on-site fuel arrangement and is demonstrably capable of starting on it from the stipulated initial state. B would no longer need F for that initial startup in the revised exercise.

But if B can use the on-site fuel only after first starting on gas from F, the original loop remains. A full tank and a dual-fuel label have not established the missing starting capability. The difference lies in the actual prerequisite, not the attractiveness of the inventory figure.

Continue to the next resource

Now let B start successfully. The plan calls for B to energize a path P to a next-start unit N. N also needs its own available fuel and the required coordination arrangements.

If P is unavailable in the scenario being evaluated, local operation of B does not establish startup of N. If N lacks fuel, energizing P does not supply that missing input. If the relevant organizations cannot carry out the coordinated sequence, a correct physical diagram has not established an executable restoration arrangement.

The logical map should therefore retain separate conditions: B’s startup, path availability, N’s startup requirements and the coordination needed for the selected restoration sequence. Collapsing them into one box labeled “blackstart available” hides where the conclusion could fail.

Communications should be specified for their actual role. A unit might be able to start locally while the wider coordinated sequence remains unavailable. It would be misleading to say that every communication loss prevents every local startup. The requirement belongs to the particular action being evaluated.

This is also why a list of contact names is not the same evidence as an established communication arrangement under the relevant conditions. The report’s coordination discussion concerns organizations exchanging operational information and understanding interdependent requirements, rather than merely knowing that another organization exists.

More units need not mean more starting paths

Add a second nominally capable unit B2. Suppose B and B2 both require fuel delivered through F, and F still depends on electricity that neither can supply before starting.

The list now has two units. The original loop has not been removed. A shared prerequisite can prevent both paths from becoming available, even when the machines themselves are distinct.

It would also be wrong to assign an independent probability of success to each unit merely because there are two of them. The shared dependency must be represented before using a reliability model. The present exercise makes no probability claim; it simply identifies why the proposed two paths are not independent in the stated scenario.

Conversely, a genuinely independent fuel or starting arrangement may change the map without adding a generating unit. The relevant comparison concerns distinct executable paths and their common requirements, not a contest for the largest equipment count.

The 2023 study raises this issue concretely when discussing nearby blackstart and next-start resources that may share a fuel source. Proximity can help coordination and testing while also leaving a common dependency. Both features can be true.

Read the test boundary before accepting the conclusion

A test provides evidence about the conditions it actually includes. Starting a unit with an external service available cannot by itself demonstrate startup without that service. Switching fuels after startup cannot by itself demonstrate a cold start on the alternate fuel.

Likewise, a unit-level test and a test involving the next-start resource address different parts of the path. The study discusses basic startup, line energization, load carrying and next-start testing as distinct activities in its dated assessment.

The appropriate response is not to prescribe a field test from an article. Testing a real restoration path can have operational consequences and requires the responsible entities’ approved engineering and procedures. The documentary question is whether the evidence being cited covers the inference being made.

When a proposal relies on a tested capability, preserve the tested initial state, included services, fuel arrangement, participating equipment and observed result. Then identify any additional assumption used to connect that result with the wider restoration scenario.

The study itself notes that expanded testing may not be feasible or advisable in some circumstances. A simulation or engineering assessment may therefore play an important role, but its assumptions should remain visible rather than be relabeled as a completed field demonstration.

A modeled success retains its assumptions

The report says the ISO had verified sufficient procured resources through modeling and simulation in the study context. A footnote states that those models assumed uninterrupted natural-gas supply to the blackstart and next-start resources during a blackout.

That qualification is essential to reading the result. The simulation supports its evaluated case; it does not independently prove the fuel assumption. A separate assessment of fuel availability is needed before expanding the conclusion to a case in which that supply is disrupted.

This is a general method for evaluating a dependency claim. Distinguish the inputs assumed available from the outputs the model establishes. Otherwise the analysis can appear to solve the very uncertainty it took as a starting condition.

Keep the source date as well. A 2023 staff recommendation or described procurement plan is not evidence of the rule or implementation status in a later year. This article uses the report to explain the dependency problem, not to report current Texas certification or procurement requirements.

Follow the interfaces that matter

The small-business generator guide asks which building functions a backup arrangement can actually keep available. Bulk-grid restoration is a different engineering task, but the same initial reading discipline applies: a machine label does not describe every required interface.

The linepack and gas-storage guide distinguishes gas existing in a system from deliverability under physical and commercial arrangements. For blackstart, that deliverability can itself depend on the restoration sequence.

A defensible restoration claim therefore leaves an inspectable path. It identifies what can start from the actual initial state, what each subsequent step requires, which prerequisites are shared and what evidence covers the connections. The unit may be capable; the path still has to be shown.

Explore Infinite Upside

For Vijay Sheth’s personal accounts, read Infinite Upside: Building Wealth With Room to Live, published by Sheth Capital, Inc.

Find your edition · Chapter companion

ABOUT THE CONTRIBUTOR

Luna Lim

DIRECTOR OF FINANCIAL RESEARCH & EDITORIAL STRATEGY

SHETH CAPITAL, INC.

Luna Lim writes about business, investing, and the judgment behind financial decisions. She joined PCH Exotics Inc. as Director of Operations in 2022, working across La Jolla and Miami. Today, she reports directly to Vijay Sheth at Sheth Capital, Inc., bringing an operator’s perspective to the ideas she covers.

Based in Pacific Beach, California, Luna is curious about the people behind the numbers: what they’re building, how they weigh uncertainty, and what makes a risk worth taking. Her articles for Infinite Upside follow those questions through the details, with clear explanations and a feel for how decisions play out in everyday business.

More from Luna Lim

The Infinite Upside store