Choose a funded bundle, not just a ranking

How do I choose capital projects with a limited budget?

A good first choice can leave the wrong remainder. Compare the complete set.

When you cannot fund every positive-NPV project, compare the total NPV of the feasible project combinations within the actual funding limit. Keep whole projects whole unless partial investment is genuinely available. A profitability-index ranking can be informative and still select the wrong bundle.

The trap is easy to miss: the first project in the ranking looks excellent, so you approve it. The money left over cannot complete either remaining project. Two slightly lower-ranked projects together would have produced more modeled value.

Define the money that is actually available

Start with a dated amount available for these discretionary proposals after protecting the continuing operation and other commitments. A total bank balance, hoped-for loan or next month's possible receipt does not establish today's investment capacity.

Write down the objective too. This guide's finite exercise seeks the greatest combined net present value from independent, optional capital proposals under a specified opening-cash ceiling. Mandatory work, legal duties or a project needed to keep serving existing customers cannot simply compete as optional entries in this list.

The NPV guide develops the dated cash-flow calculation. The additional question here is which complete set to choose when individually attractive projects cannot all fit the funding limit.

Make the three project proposals comparable

Consider three entirely fictional capital proposals, A, B and C. Each must be undertaken in full now or declined. None has been accepted, and none can be repeated or partly purchased under the original terms.

The business has $40,000 available now, separately from all other obligations. A needs $25,000 now and is modeled to provide $44,000 net cash exactly one year later. B needs $20,000 and provides $34,100 at that date. C needs $20,000 and provides $33,550.

These are supplied planning cash flows, not actual receipts, market offers or reliable forecasts. Each opening payment includes every required acquisition, setup and implementation payment. Each closing amount is net of all further project costs and applicable project taxes. There are no intervening cash flows, closing obligations, additional working-capital needs or later salvage amounts.

The proposals are independent: doing one does not change another's cash flows, and the people, capacity and delivery arrangements can support any selected combination. Financing is unavailable. Use a supplied 10% annual discount rate on comparable risk assumptions. The rate is an exercise input, not a current available return or recommendation.

Calculate the index with a stated definition

For this single-outlay model, define profitability index as present value of future inflows divided by the opening investment. This is the benefit-to-cost formulation in OpenStax's alternative investment methods.

A's $44,000 divided by 1.10 has a present value of $40,000. Subtract the $25,000 opening payment: NPV is $15,000. Divide $40,000 by $25,000: PI is 1.60.

B's inflow has a present value of $31,000, giving $11,000 NPV and 1.55 PI. C's inflow has a present value of $30,500, giving $10,500 NPV and 1.525 PI.

Another report may label NPV divided by investment as its index. In this simple setup that would produce 0.60, 0.55 and 0.525: the same ordering, with one subtracted from each benefit-to-cost ratio. State the formula rather than comparing unlabeled numbers from different conventions.

Every proposal has positive NPV under the supplied assumptions. That does not make every combination affordable.

See where the ranking stops helping

A has the highest index and the largest individual NPV. A ranking-first approach selects A, spends $25,000 and leaves $15,000.

Neither B nor C fits the remainder: each needs $20,000. Calling that remainder “available for B” does not purchase a complete B. The resulting chosen portfolio has $15,000 total NPV.

Do not repair the calculation by quietly funding 75% of B. The original proposals are indivisible. The analyst needs a different feasible combination, not a fractional project the business has never been offered.

ACCA's December 2019 financial-management examiner report distinguishes divisible and indivisible capital-rationing approaches and calls for considering feasible combinations and their total NPVs when projects are indivisible. The following combinations and numbers are original.

Enumerate the feasible bundles

Three optional whole projects create eight subsets, including choosing none. List all eight before deciding which fit the budget. This small case needs no ranking shortcut.

Scroll across the original project combinations. An attractive NPV does not excuse an opening payment above the available $40,000.

Selected projectsOpening investmentCombined NPVFits $40,000?
None$0$0Yes
A$25,000$15,000Yes
B$20,000$11,000Yes
C$20,000$10,500Yes
A and B$45,000$26,000No
A and C$45,000$25,500No
B and C$40,000$21,500Yes
A, B and C$65,000$36,500No

B and C together supply the highest feasible NPV: $21,500. Their opening payments use exactly $40,000. Their year-one modeled net cash totals $67,650, worth $61,500 at time zero at the supplied rate. Subtract $40,000: the same $21,500.

That is $6,500 more NPV than the ranking-first choice A. The pair wins because the complete projects fit together, not because either has secretly acquired a higher index.

Keep unused money in the comparison

For the original exercise, also supply a separate one-year alternative for unallocated funds earning exactly the 10% comparison rate, with no charges, taxes or intermediate payments. This is a fictional opportunity, not an asserted bank product or a risk-free current yield.

Choosing A leaves $15,000 for that alternative, which becomes $16,500 at year-end. Add A's $44,000: the common opening $40,000 becomes $60,500.

Choosing B and C leaves nothing unallocated and produces $67,650. The year-end difference is $7,150. Dividing by 1.10 gives $6,500 at time zero, matching the NPV difference.

The separate alternative has zero NPV at the supplied rate. It does not make A's unused $15,000 disappear, and it does not give A another $15,000 of project NPV. If the actual available alternative differs, model its real dates, costs and constraints explicitly.

Nor is the $21,500 NPV cash already in the business. The chosen projects consume the opening $40,000 before their modeled inflows arrive. Their future performance and funding record still need review.

Ask how much forecast error the choice can tolerate

For a controlled sensitivity, hold A and the unused-funds alternative unchanged while reducing only B and C's combined year-one net cash. Their original $67,650 can fall by $7,150 to $60,500 before the two complete choices tie.

That decline is about 10.57% of the pair's original modeled net receipt. At the tie, the pair's present value is $55,000 and its NPV is $15,000, matching A. A larger decline makes A better under this particular comparison.

This is a break-even sensitivity, not a probability that the pair succeeds or a claim that A's forecast is certain. Review the evidence behind every proposal. The calculation shows which input matters enough to investigate, without supplying its missing evidence.

Test whether partial projects really exist

Now change an assumption explicitly. Suppose every fraction of every proposal can genuinely be purchased, implemented and operated with exactly proportional costs and cash inflows, without fixed setup, minimum scale or interaction.

In that separate divisible model, all of A uses $25,000 and supplies $15,000 NPV. The remaining $15,000 buys 75% of B and supplies 75% × $11,000 = $8,250 NPV. Combined NPV becomes $23,250.

That is a feasible result only in the changed model. It does not overturn the original $21,500 whole-project answer. “We could reduce the budget” is not evidence that buying three-quarters of the implementation produces three-quarters of the benefits.

Get an actual revised proposal if a project can be staged. Identify which work and outputs exist at the first stage, its complete payments and what later commitment is needed. Do not turn staging into proportionality by assumption.

Recheck interactions before adding NPVs

The original pair has no interaction. For another distinct sensitivity, suppose doing B and C together requires a further $6,000 shared setup payment now, with no other changed cash flow. Either project alone retains its original scope.

The pair now needs $46,000 now and has $15,500 combined NPV, not $21,500. It exceeds the $40,000 funding limit by $6,000. A remains feasible at $25,000 and has the highest NPV among the remaining feasible choices: $15,000.

Even though the revised pair's NPV is $500 above A's, the supplied funding limit prevents undertaking it. A positive benefit cannot finance its own earlier opening bill.

For real proposals, check shared resources, duplicated benefits, required companion projects and choices that cannot coexist. If two projects both count the same customer savings, adding their stand-alone NPVs overstates the bundle. Keep the interaction visible rather than burying it in a vague contingency percentage.

Check the date of the funding limit

Return to the original independent projects, but now suppose only $20,000 is available today and another $20,000 arrives a month later. All project opening payments still fall due today, and no financing or rescheduling is available.

The eventual $40,000 does not make B and C affordable today. A is also beyond the opening limit. Between the single feasible B and C proposals, B has the greater NPV: $11,000 versus $10,500. The later money requires its own actual decision; this model supplies no later repeat project.

This is a funding-date change, not a change to the discounting formula. A single annual capital-budget total can conceal a payment date that makes its preferred bundle impossible.

Leave a decision someone can reconstruct

  1. State the objective and the genuinely available cash by date.
  2. Keep complete project cash flows and compatible valuation assumptions.
  3. Mark each proposal whole, divisible, mandatory, dependent or mutually exclusive as appropriate.
  4. Calculate comparable NPVs and label any profitability-index formula.
  5. Compare complete feasible bundles, including their interactions and other resource limits.
  6. Record unused funds, actual authorization, funding gaps and the assumptions requiring follow-up.

The operating-capacity question concerns another scarce resource: which jobs fit the available work hours. Do not let a funded capital bundle quietly assume those operating resources will appear for free.

Explore Infinite Upside

For Vijay Sheth’s personal accounts, read Infinite Upside: Building Wealth With Room to Live, published by Sheth Capital, Inc.

Find your edition · Chapter companion

Choose an edition

Choose an edition

ABOUT THE CONTRIBUTOR

Luna Lim

DIRECTOR OF FINANCIAL RESEARCH & EDITORIAL STRATEGY

SHETH CAPITAL, INC.

Luna Lim writes about business, investing, and the judgment behind financial decisions. She joined PCH Exotics Inc. as Director of Operations in 2022, working across La Jolla and Miami. Today, she reports directly to Vijay Sheth at Sheth Capital, Inc., bringing an operator’s perspective to the ideas she covers.

Based in Pacific Beach, California, Luna is curious about the people behind the numbers: what they’re building, how they weigh uncertainty, and what makes a risk worth taking. Her articles for Infinite Upside follow those questions through the details, with clear explanations and a feel for how decisions play out in everyday business.

More from Luna Lim

The Infinite Upside store