The contractor hands over the keys. The tenant starts installing equipment. A week later, an invoice arrives for operating expenses. The tenant thought rent did not start until the shop opened. The lease had several other dates in mind.
Commercial leases can distinguish delivery, early access, lease commencement, rent commencement and the date the business opens. The agreement decides what each date means and which obligations begin with it. Before signing, put those dates and responsibilities on a shared calendar, including what happens if construction, permits or either party’s work runs late.
The goal is not to find a universal rule that rent begins at opening. It is to know what the particular lease says before a planned opening becomes a cash-flow surprise.
The keys do not start every clock
Delivery may be the landlord’s handover of the space in a contractually described condition. Early access may let a tenant enter to measure, wire or install equipment before the lease’s main commencement. Lease commencement can start the term and certain other duties. Rent commencement is the date a specified rent obligation begins. The business’s opening date is an operational event and need not be any of those dates.
Those are categories to check, not standard definitions. A lease can combine some dates, use different labels or tie a date to a condition. It can also distinguish base rent from taxes, insurance, utilities or common-area charges. Ask counsel to read the lease together with the work letter and exhibits; a summary sheet may not contain the condition that changes the calendar.
One SEC-filed office lease addresses permitted early entry separately from rent obligations and defines delivery work in its own terms. It is a single contract example, not a rule for other tenants or a promise that every early-entry period is free of charges.
A fictional handover with two charges
Assume a fictional lease delivers a space on May 1. Its stated terms give the tenant access that day, charge $2,000 of operating expenses for the full month of May, and start base rent 30 days after May 1, on May 31. For this simplified example, the agreement states that base rent is $12,000 per 30-day month and prorates the first month at $400 per day. The tenant opens on June 15.
Under those supplied terms, May’s base rent for May 31 is $400. May’s identified charges are $400 plus $2,000, or $2,400, before utilities, construction costs, deposits and anything else excluded from the example. Opening on June 15 does not move the assumed May 31 base-rent start. The tenant should budget the June charges separately under the lease; the example does not decide when June rent is due or calculate its full bill.
Suppose the lease instead expressly starts both base rent and those operating expenses on opening day, with all other assumptions changed only as needed to make that alternative workable. The May charges for those two items would be zero. That is a different negotiated term, not a correction to the first calculation. Real leases use different month lengths, prorations, free-rent periods and expense definitions.
“Substantially complete” still needs a definition
A landlord may promise work before delivery. A lease can define completion by reference to approved plans, required inspections, access, functioning services or other conditions. It may also allow minor remaining items on a punch list. The exact definition matters: a missing trim piece and an unfinished system that prevents the tenant’s required work are different practical problems, but the contract determines the consequences.
A filed lease example defines substantial completion of landlord work while allowing specified minor punch-list items that do not interfere with the tenant’s work. That is one transaction’s wording. Do not assume the same tolerance, inspection or remedy is present in another lease.
Ask who inspects the work, who identifies unfinished items, how the list is agreed and when each item must be corrected. Record the condition of the space at handover and keep the relevant notice and response. A punch list may preserve unfinished work for follow-up; it does not automatically postpone every payment or authorize the tenant to withhold rent.
Whose delay, and what does the lease do with it?
Buildout depends on a chain: plans, approvals, permits, materials, landlord work, tenant work, inspections and installation. A delay can have more than one cause. The lease may distinguish a landlord delay from a tenant delay, permit delay or another event, with particular notice and documentation requirements.
Read any “deemed” completion or commencement language carefully. Some contracts describe a date as having occurred for a specified calculation even though physical work finishes later, if defined conditions apply. A real lease’s wording, facts and applicable law control. Do not infer that an unfinished space either definitely starts or definitely postpones rent without reviewing that language.
For a project team, a simple delay log can prevent a calendar argument from becoming a memory contest. Record the affected task, original date, event, date each party was notified, supporting correspondence and the decision or outstanding disagreement. Keep actual completion separate from a date asserted for contractual purposes. Send notices in the manner the agreement requires, with qualified advice when the consequences are material.
Free rent is not a synonym for no cost
A concession may waive base rent for a defined period while leaving other obligations in place, or it may work differently. Identify the first and last day, the charges included, whether the period begins at a fixed date or an event, and any conditions or consequences stated in the lease. “Two months free” in a presentation is not enough to build the cash forecast.
Put the tenant-improvement allowance on a separate line. A reimbursement may depend on approved work, invoices, lien documentation or other conditions, and it may arrive after the tenant pays a contractor. Our tenant-improvement allowance guide follows that reimbursement question. A promised allowance does not automatically pay the next invoice on the day it arrives.
Also check deposits, insurance, permits, utilities, security and service contracts. Some may be due before the business serves its first customer. The right budget follows actual due dates and available cash, not only the first month in which revenue is expected.
Can the business legally open?
A lease date, a contractor’s completion statement and a government approval answer different questions. Depending on the space and activity, a certificate of occupancy or separate operating permits may be relevant. The commercial occupancy guide explains those distinctions; ask the appropriate local authority and project professionals about the actual property.
If an approval is delayed, check both the public requirement and the lease’s allocation of cost and delay. A tenant should not assume that a rent invoice establishes permission to operate. Equally, a pending permit does not automatically change a contractual payment date. Get the specific answer from the agreement and qualified local advisers.
A handoff the finance team can use
Before work begins, make one dated register with the delivery condition, authorized access, commencement triggers, free-rent terms, expense start dates, inspections, allowance submissions and responsible people. Attach the clause or exhibit behind each entry. Mark a date as estimated until the event or notice required by the documents has actually occurred.
Update the register when the project changes. If a contractor finds an unresolved condition, the project manager needs to know who decides it; the bookkeeper needs to know what the lease says about the next bill. Those may be the same conversation, but they are not the same decision.
At handover, reconcile the landlord’s notice and invoices with the completion evidence, punch list and lease. If something is disputed, preserve the records and ask counsel about the required response and deadlines. Do not let a disputed date vanish into an email chain while the accounting system quietly treats it as settled.
Know when the doors can open. Know when each bill starts, too, ideally while there is still time to negotiate.