How do I estimate the next batch with a learning curve?

The average through eight units is not the time for the next four. Subtract totals before pricing the new commitment.

To estimate a future batch with a cumulative-average learning curve, calculate modeled total production time at the new cumulative quantity and subtract modeled total time at the quantity already completed. Do not multiply the new cumulative average by the new batch alone. That average still includes earlier, slower work.

The useful answer has two parts: the hours implied by the model, and the evidence that makes the model suitable for this commitment. A tidy curve does not make the next team faster, supply missing training or guarantee that a fixed-price job will fit the calendar.

Identify which learning curve you mean

In a cumulative-average model, a stated learning rate applies to average time per unit each time cumulative output doubles. An 80% rate means the new cumulative average becomes eighty percent of its previous value at each doubling. It does not mean an eighty percent reduction.

ACCA's learning-curve explanation makes that cumulative-average distinction. It also notes the importance of repetition, workforce continuity and the possibility that learning ends. Its discussion does not establish a universal rate for a business quoting unfamiliar work.

Write the model label beside the percentage. A curve for the time of an individual numbered unit is a different model. Applying an individual-unit interpretation to a cumulative-average rate changes the estimated totals.

Also identify the measured activity. Production labor hours, machine occupancy and elapsed delivery time are different resources. A reduction in one cannot automatically be applied to all the others.

Build an original doubling table

Consider an entirely fictional workshop making identical custom assemblies in a continuing process. The first assembly takes twenty production labor hours. For this teaching case, the supplied model is an 80% cumulative-average curve through the eighth assembly.

The model concerns direct production only. Inspection, job setup and materials are deliberately separate. Quality and the finished specification remain unchanged; the calculation does not obtain speed by omitting required work.

The table follows directly from the supplied model. Each time cumulative quantity doubles, multiply the cumulative average by 0.8. Multiply that average by cumulative quantity to obtain total production hours.

Scroll across the original model. A cumulative average includes every assembly from the first through the stated quantity.

Cumulative-average learning model: original doubling table
Cumulative assembliesAverage production hours per assemblyCumulative production hours
12020
220 × 0.8 = 162 × 16 = 32
416 × 0.8 = 12.84 × 12.8 = 51.2
812.8 × 0.8 = 10.248 × 10.24 = 81.92

These are original supplied planning values, not production observations, a measured learning rate or results achieved by the author. No customer demand or accepted order is created by filling in the table.

Subtract the work already inside the average

The second assembly alone takes 32 − 20 = 12 hours under the model. It does not take sixteen hours. Sixteen is the average of the first two: twenty plus twelve, divided by two.

Assemblies three and four together take 51.2 − 32 = 19.2 hours. Their combined average is 9.6 hours each. That group average does not say the third and fourth individually take the same time.

Now suppose the workshop has completed the first four assemblies. A customer is considering four more of the same specification. Their modeled direct production time is 81.92 − 51.2 = 30.72 hours.

The next four's average is 30.72 ÷ 4 = 7.68 hours. That differs from the 10.24-hour cumulative average through all eight. The earlier slow work remains inside 10.24.

Multiplying 10.24 by four would give 40.96 hours, overstating this model's next-batch estimate by 10.24 hours. Using 81.92 as the next batch would include the first four's 51.2 hours again.

Use the formula with the same labels

For quantities between doublings, the conventional cumulative-average formula is average time = a × n raised to b, where a is the first unit's time, n is cumulative quantity and b = log(learning rate) ÷ log(2). ACCA's formula sheet defines these terms.

Total time is n multiplied by that average. Estimate an interval by subtracting the earlier cumulative total from the later one. Keep the learning rate as a decimal in the logarithm and use consistent hour units.

Our worked doubling table needs no logarithmic approximation: 0.8, 0.64 and 0.512 are the exact successive multipliers. Preserve adequate precision in the calculation and round only at the appropriate reporting or scheduling stage. A small rounding difference should not quietly become a missing paid task.

A formula extrapolated indefinitely would keep changing the averages. This case expressly stops its assumption at eight assemblies. It supplies no forecast for the hundredth assembly or evidence of a permanent productivity trajectory.

Check what the rate implies before relying on it

The original table implies an 80% learning rate because the first two units' sixteen-hour average is 80% of the first unit's twenty hours. Dividing the second unit's twelve hours by twenty gives 60%, which is not the cumulative-average rate. Keep the numerator's meaning intact when estimating a rate from records.

For an independent before-production comparison, use the same twenty-hour first unit but assume a 90% cumulative-average curve instead. This is a different model, not a replacement for a shared observed production history.

Under that alternative, the first four average 16.2 hours and total 64.8; the first eight average 14.58 and total 116.64. The next four therefore require 51.84 modeled production hours. That is 21.12 more than the original 30.72.

A 90% rate represents less improvement per doubling than 80%, not more. Neither percentage has been established as the workshop's actual rate. The comparison identifies how consequential that evidence is before a proposed quote depends on the faster curve. Do not average two unsupported rates and call the result validated.

Put the remaining work back into the job

For the proposed four additional assemblies, suppose the complete incremental job scope requires the modeled 30.72 production hours, another two paid inspection hours and five paid setup-and-administration hours. Those categories do not overlap.

Every hour is paid at a complete incremental $40. Materials cost $150 per new assembly, fully delivered and usable. There are no other incremental job charges under these expressly supplied terms.

The job therefore needs 37.72 paid hours, costing $1,508.80, plus $600 materials. Total modeled incremental job cost is $2,108.80.

The customer is considering a proposed price of $600 per assembly, or $2,400 for four. That would leave $291.20 after the stated incremental job costs, toward unchanged company overhead and profit. It is not a claim of total company profit, an accepted sale or an optimal price.

The first four's historical costs belong in the business's wider records. They are not another future cash payment caused by accepting these next four. Equally, excluding sunk hours from the next-batch estimate does not make those earlier costs disappear from the economics of developing the product.

Check money and hours before the promise

The fictional workshop has $2,200 actually available for the proposed job after protecting all other obligations. The full $2,108.80 is required before any customer payment arrives; no deposit or supplier credit has been arranged. The remaining funding margin is $91.20.

Forty suitable labor hours are available in the required delivery window after existing commitments. The 37.72 modeled hours fit with 2.28 hours left. The necessary equipment and materials are available within this limited scope.

These are planning inputs, not proof the job has been completed or that the modeled production duration will occur. A fixed delivery promise still requires an appropriate operating decision. The price-basis guide separates an estimate from a commitment to complete a defined result at a stated price.

Stress a required task the curve does not cover

In a separate branch, the actual scope review identifies six additional paid training hours needed before this job can proceed. They are outside the production curve and the earlier setup allowance. No other input changes.

The extra training adds $240. Incremental job cost becomes $2,348.80. Against the proposed $2,400 revenue, only $51.20 remains toward unchanged overhead and profit.

More immediately, the available $2,200 leaves a $148.80 funding gap. Required labor becomes 43.72 hours, exceeding the forty-hour window by 3.72 hours. A positive modeled contribution has not supplied cash or capacity.

No overtime, unpaid owner work or postponed inspection is assumed. The business needs an actual supported change to resources, timing, scope or terms before it can make the original promise. Changing a learning-rate cell would not remove training the work genuinely requires.

Compare a unit-time model before using the rate

The label “80% learning curve” is not enough to select a calculation. For a separate before-production sensitivity, keep a fictional first-unit time of 20 hours but use an 80% individual-unit curve rather than the earlier 80% cumulative-average curve. This is an alternative forecast, not a revised description of the first four units already completed in the original example.

Under the individual-unit formulation, each time the unit number doubles, the time for that numbered unit is 80% of the earlier numbered unit’s time. Unit 1 takes 20 hours, unit 2 takes 16 and unit 4 takes 12.8. Under the cumulative-average model, by contrast, 16 is the average of units 1 and 2, so unit 2 alone takes 12. The equal 80% labels are attached to different quantities.

For this independent sensitivity, specify the individual-unit formula T(n) = 20 × n^b, with b = log(0.8)/log(2), approximately −0.321928. Unit 3 then takes approximately 14.0421 hours. Summing the individual modeled times for units 1 through 4 gives approximately 62.8421 hours, not the cumulative-average model’s 51.2 hours through unit 4.

Applying the same individual-unit formula to units 5, 6, 7 and 8 gives approximately 11.9127, 11.2337, 10.6898 and 10.24 hours. Their unrounded sum is approximately 44.0762 hours, compared with 30.72 hours for units 5–8 under the original cumulative-average model. The difference is approximately 13.3562 hours. The unit-8 time of 10.24 is not the average for all eight units under the individual-unit model.

For this separate planning sensitivity, return to the base job without the additional training branch. Retain its separate 2 inspection hours, 5 setup-and-administration hours, $40 complete hourly cost and $600 materials. The individual-unit forecast would require approximately 51.0762 paid hours and $2,643.05 of incremental job cost. It exceeds the stipulated 40-hour capacity by about 11.0762 hours and the $2,200 available funding by about $443.05; the proposed $2,400 price is about $243.05 below those modeled incremental costs. These figures use unrounded production hours before final rounding.

This comparison is useful before making the promise, but it does not prove either model describes the workshop. The individual-unit alternative predicts a different first-four total, so do not combine it with the original branch’s assumed completed 51.2 hours as though both described the same observations. Gather comparable unit-level records, identify the applicable formulation and measured work, and test the forecast before relying on it. A change in product, staffing or nonproduction tasks can change the result.

The U.S. Government Accountability Office’s 2020 cost-estimating guide, appendix VII, distinguishes individual-unit and cumulative-average learning formulations. It supports the model distinction, not the invented rate, hours, customer price or conclusion for an actual business. Neither curve is a guarantee that work will accelerate or that a quotation is appropriate.

Test the model against comparable work

Retain completed quantities and the production hours associated with them, using a stable definition. Separate setup, inspection, rework and interruptions so an apparent learning improvement is not merely a changed time boundary.

Compare the model with actual comparable intervals as they finish. A total consistent with the curve is useful evidence, but a few matching aggregates do not prove the next group will follow it. Changed designs, different people or a lengthy interruption need fresh examination.

Keep the original forecast beside the actual record. Investigate a difference before attributing it to effort, skill or waste. The next-customer guide follows resource commitments that change with volume; a learning assumption should not conceal an additional staffing or equipment step.

Leave an estimate that can be reviewed

  1. Name the repeated output and measured resource.
  2. Identify cumulative-average or individual-unit model explicitly.
  3. Retain the first-unit basis, learning-rate evidence and valid range.
  4. Calculate cumulative totals and subtract the completed interval.
  5. Add every required task outside the curve without overlap.
  6. Check full job funding, available capacity and a consequential failure branch.
  7. Preserve the original estimate and compare it with completed work.

Explore Infinite Upside

For Vijay Sheth’s personal accounts, read Infinite Upside: Building Wealth With Room to Live, published by Sheth Capital, Inc.

Find your edition · Chapter companion

Choose an edition

Choose an edition

ABOUT THE CONTRIBUTOR

Luna Lim

DIRECTOR OF FINANCIAL RESEARCH & EDITORIAL STRATEGY

SHETH CAPITAL, INC.

Luna Lim writes about business, investing, and the judgment behind financial decisions. She joined PCH Exotics Inc. as Director of Operations in 2022, working across La Jolla and Miami. Today, she reports directly to Vijay Sheth at Sheth Capital, Inc., bringing an operator’s perspective to the ideas she covers.

Based in Pacific Beach, California, Luna is curious about the people behind the numbers: what they’re building, how they weigh uncertainty, and what makes a risk worth taking. Her articles for Infinite Upside follow those questions through the details, with clear explanations and a feel for how decisions play out in everyday business.

More from Luna Lim

The Infinite Upside store