The hotel’s purchase price looks workable. Then the brand sends a property-improvement plan: guest rooms, public areas, signage and a deadline. Suddenly the building is not the only thing being bought. The buyer is also taking on a construction project that may have to happen while guests are sleeping upstairs.
A hotel property-improvement plan, often called a PIP, identifies work a brand or other relevant party requires or proposes for a particular property under the applicable arrangement. To evaluate it, obtain the actual plan and franchise documents, price the full scope, understand the deadline and approval process, and model construction disruption and funding. A preliminary brand list is not a contractor’s guaranteed price.
Start with the property-specific plan, not a cost per room borrowed from another deal. The important questions are which items are required, when the work must be completed, and whether the hotel can fund and operate through it. The answers depend on the plan, contracts and building.
Why might a hotel receive a plan?
A plan may arise in connection with a new franchise, conversion of an existing hotel, transfer, renewal or another review under the relevant agreement. It can address visible items such as guest-room finishes and signs as well as less photogenic systems, accessibility, technology or other standards. The scope and trigger depend on the documents and property.
One historical Hyatt franchise agreement filed with the SEC discusses a PIP and renovation plans for conversion of an existing hotel. It is an example of one document, not evidence of current terms at Hyatt or any other brand. Request the current, property-specific plan and agreement before assuming a historical form applies.
A brand’s desired improvements and local legal requirements are related but not interchangeable. A particular project may require permits, code review or agency approvals independent of the brand’s review. Ask the design team what is needed and who bears the cost and schedule risk.
Turn the list into a scope of work
Read each item with the property team. Is the work a replacement, repair, upgrade, inspection or further study? Does it apply to every room, a sample, a public area or a specific system? Are there approved products, design standards or brand review stages? Identify what is mandatory, what is conditional and what remains an assumption.
Put each line into a scope register: required work, location, quantity, specification, completion date, approval needed and the person pricing it. A line saying “refresh bathrooms” is not enough for a reliable bid. Paint and fixtures in every room are a different project from replacing waterproofing, plumbing and tile.
Compare the plan with a physical inspection and the existing building records. An improvement list may not identify every concealed condition. Ask the contractor and architect what they have verified, what remains inaccessible and how an unexpected finding would be priced and approved. A contingency is not a substitute for understanding the exposure it is meant to cover.
A fictional 100-room hotel
Suppose a fictional buyer estimates the required guest-room work at $8,000 per room for 100 rooms. That component is 100 × $8,000 = $800,000. The buyer separately estimates $250,000 for public areas and $150,000 for design, permits and other identified project costs. The subtotal is $1,200,000.
Assume the buyer adds a 10% contingency to that subtotal for this illustration. Ten percent of $1,200,000 is $120,000, producing an initial project budget of $1,320,000. These amounts and the percentage are invented; they are not a market benchmark or a quote for a real plan.
Now add a separate fictional $180,000 estimate for operating disruption that is not already included in the project costs. The identified combined capital-and-disruption exposure is $1,500,000. It is not the hotel’s total purchase cost, and it excludes financing, taxes, timing effects and any other unlisted costs. If disruption was already included in another line, adding it again would double-count.
Check the estimate against actual bids, scope and timing. A $1.32 million project budget is not a binding construction price just because it has been placed in a spreadsheet. The buyer needs to know which assumptions are supported, which are provisional and who pays if they change.
The purchase price is not the full investment
Place the purchase price, transaction costs, PIP, working capital, financing costs and reserves in the same sources-and-uses model. Identify any existing capital reserve and whether its balance is available for the work, subject to the relevant agreements. Do not count the same reserve both as unrestricted cash and as funding for a separate obligation.
Ask the lender how it treats the project. Will it require an escrow, a completion guarantee, approved budgets, inspections or evidence of brand approval? Put expected invoices and draw dates on the same calendar. If the owner must pay a contractor before the lender releases funds, the project can have a cash gap even when the overall financing appears sufficient.
Model cost overruns and schedule delays separately. A 10% construction overrun and three additional months of carrying costs are different exposures. Clarify whether the purchase agreement allocates any plan-related cost between buyer and seller, whether a holdback applies and what happens if the parties do not receive the expected plan before closing.
Renovation changes the operating calendar
Put the construction sequence beside the reservations calendar. For each phase, mark which rooms and floors leave inventory, the planned return date, the approval needed before resale and who can release them. Add the effects on meeting space, food service, access, noise, dust, guest safety and staff workload. Give the operator the same updated schedule as the contractor and brand; a room that looks finished is not necessarily ready to sell.
Estimate unavailable room nights using a dated schedule, not only a total number of rooms. If ten rooms are offline for 30 nights, that is 300 unavailable room nights under the supplied assumptions. It is not automatically 300 lost bookings: demand, occupancy, rates and the ability to relocate guests affect the financial result.
Coordinate with the contractor, operator and brand on guest communications and safety procedures. Keep the schedule current when materials, permits or work sequences change.
Read the deadlines and consequences
Identify the effective date, interim milestones, completion deadline, extension procedure and any required reporting. Ask who decides whether an item is complete and what evidence is required. Does the plan expire or change if the sale is delayed? Does the franchise agreement allow changes to standards during the work? Those answers belong in the actual documents.
Do not assume a brand’s review replaces a contractor’s duty to build correctly or a local authority’s permit process. Ask counsel and the project team to explain the roles and approval sequence. A design can satisfy a brand review and still require other approvals before construction or occupancy.
If a milestone is at risk, use the notice and extension process in the agreement and preserve the response. A request for more time is not an approved extension. Similarly, a contractor’s estimate of completion is not proof that the brand or authority has accepted the work.
Compare bids on the same assumptions
Give bidders the same scope and request exclusions, allowances, lead times, taxes, permitting responsibilities and work-hour assumptions. Put those differences in a comparison table before ranking the totals. A low bid excluding demolition, electrical upgrades or night work may simply have left a cost for someone else to price.
Look for long-lead items, approved-vendor requirements and dependencies between trades. Ask how substitution requests will be handled and whether a proposed product needs brand approval. A cheaper substitute is not a saving if it delays opening or is later rejected.
Review contingency and change-order authority. Who can approve extra work, at what amount, and what documentation is needed? If the hotel manager, owner and lender all have approval roles, a clear sequence can prevent an urgent discovery from becoming an untracked invoice.
Treat future revenue as a hypothesis
A renovated hotel may be more competitive, but a PIP does not guarantee higher occupancy, a higher average daily rate or a sale at a particular price. Model several cases and state why each assumption might be reasonable. Compare the hotel with relevant properties and consider how much work is needed simply to maintain the current brand and market position.
Separate gross room revenue from the incremental operating contribution after relevant costs. If a fictional project produces $300,000 in additional annual room revenue but $120,000 in additional variable and operating costs under a simplified scenario, the resulting identified contribution is $180,000 before financing, taxes and other excluded costs. That example does not predict a real result or prove that all revenue is caused by the renovation.
Consider downside cases too: slower demand, lower room availability during work, an extended schedule or a plan that costs more than expected. A business may need to complete work to retain a franchise even if the immediate financial return is uncertain. That contractual need and an investment-return forecast are different reasons for proceeding.
What a buyer should request
Before committing to a transaction, request the current plan, franchise agreement, brand correspondence, inspection reports, existing capital budgets, permits, available drawings and relevant contracts. Ask whether the brand has approved the buyer, whether the existing agreement can be transferred or a new one is required, and which conditions remain open. Do not rely on a seller’s summary when the actual documents are available.
Compare the plan with the hotel’s condition and a qualified scope review. Determine what can be verified before closing, what remains uncertain and how the purchase agreement handles those uncertainties. Counsel can explain the implications of deadlines, approval rights and any remedies.
The FTC’s franchise-buying guide notes that franchisors may impose design standards and periodic renovations, and encourages prospective franchisees to investigate the full investment and obtain advice. It is general franchise guidance, not a hotel-specific cost estimate.
Questions before accepting the plan
- What exact work is required, by whom, and by which dates?
- Which specifications, products, plans and approvals are current?
- What is included in the contractor bids, and what remains an allowance or unknown?
- How many rooms and services will be unavailable during each phase?
- Who funds the work, controls reserves and approves changes?
- What happens if the brand review, permit or financing takes longer than expected?
- How do the purchase, franchise, management and loan documents allocate the risk?
The purchase decision needs three calendars in the same room: the brand’s deadlines, the contractor’s work and the hotel’s operating commitments. Add the funding schedule. If they do not fit together on paper, the problem will be more expensive to discover with guests in the lobby.
A required improvement and the money available to fund it are separate questions. The FF&E reserve guide follows deposits, restrictions and project timing.