What the project has actually earned

How do I calculate earned value for a project?

Low spending can conceal even lower progress. The useful report keeps work, cost and cash distinct.

Calculate earned value by assigning the original budget value to work demonstrably completed under agreed measurement rules. Compare it with the budget value of work scheduled by the same cutoff and the actual cost incurred for that work. Those three amounts—earned value, planned value and actual cost—answer different questions. None is automatically a bank balance, customer revenue or profit.

A project that has spent less than its full budget can still be in trouble. If it has accomplished even less of the planned work, the quiet bank account may be concealing a larger bill ahead.

Fix the scope and how work earns credit

The Department of Energy's earned-value reference identifies planned value as the budgeted cost of scheduled work, earned value as the budgeted cost of performed work, and actual cost as the cost of work performed. Its formulas compare these amounts and relate a completion estimate to actual cost plus the estimate to complete.

Before measuring, establish the authorized scope, its complete budget, the schedule and the evidence required for progress credit. Do not choose a percentage afterward because someone feels nearly finished.

A delivery receipt, accepted record or completed test can provide a boundary people can check. The appropriate measurement depends on the work. A long, indivisible task measured only at its end may need better planning detail, rather than a generous unsupported percentage.

An original $20,000 project

A wholly fictional business has a bounded internal records-conversion project with a complete original budget of $20,000. All required paid management, conversion, checking, training, equipment and other project resources are included. No unpaid owner labor or extra subscription sits outside this scope.

The four work packages and their measurement rules were agreed before work began:

  • A: approved requirements, $2,000. It earns the full budget value when accepted, otherwise zero.
  • B: twenty equally budgeted conversion packages, $8,000. Each completed and accepted package earns $400. Packages have deliberately equal budget weights in this fictional design.
  • C: final verification, $6,000. It earns the full amount only when its complete acceptance condition is met.
  • D: training and handover, $4,000. It also uses a full-completion acceptance rule.

This is a measurement model, not a quote for real records work. Its fixed boundaries make the example auditable. If actual packages differ substantially in effort or value, equal weights would need support rather than being assumed.

At the end of week three, the original schedule calls for A and all twenty B packages to be accepted. C and D are scheduled later and have zero planned value at this cutoff. A and B therefore contribute $2,000 + $8,000 = $10,000 of planned value.

The evidence instead shows A accepted and only ten B packages accepted. C has started preparation, but its acceptance condition is not met. D has not begun.

Reconcile the status record before calculating ratios

Ten accepted B packages earn 10 × $400 = $4,000. Add A's $2,000, and cumulative earned value is $6,000. C earns zero under the predetermined rule, even though some work has occurred.

The complete incurred-cost record at the same cutoff is $2,000 for A, $5,000 for B, $1,000 for C and zero for D: $8,000 actual cost. It includes all project costs incurred so far, including $1,000 still unpaid. Actual cash payments total $7,000.

The unpaid amount is a valid incurred obligation in this fictional record, not an optional future proposal. Excluding it simply because the invoice has not been paid would understate actual cost.

Scroll across to compare the same cutoff. Earned and planned values use budget amounts; actual cost records incurred amounts.

PackageFull budgetPlanned valueEarned valueActual cost
A$2,000$2,000$2,000$2,000
B$8,000$8,000$4,000$5,000
C$6,000$0$0$1,000
D$4,000$0$0$0
Total$20,000$10,000$6,000$8,000

The report is 50% scheduled, 30% earned and 40% incurred cost, each relative to the $20,000 budget. Calling the project “40% complete” because costs reached $8,000 would confuse spending with accomplishment.

C's zero credit does not prove its $1,000 was wasted. It means the work has not yet satisfied this package's earning rule. Investigate what has been done and what remains; do not grant convenient progress credit merely to make the ratio look better.

Read the cost and schedule signals

The cost performance index, CPI = earned value ÷ actual cost, is $6,000 ÷ $8,000 = 0.75. The project has earned seventy-five cents of budget value for each dollar of incurred cost. Those are budget-value units, not seventy-five cents of business income.

The cost variance is $6,000 − $8,000 = −$2,000. It compares accomplished work's budget with its incurred cost. It does not mean the entire $20,000 budget has already been exceeded.

The schedule performance index, SPI = earned value ÷ planned value, is $6,000 ÷ $10,000 = 0.60. The schedule variance is $6,000 − $10,000 = −$4,000, expressed in budget dollars.

That negative $4,000 says accepted progress has less budget value than the work scheduled by this cutoff. It does not say the project is four days late, will finish 40% late or needs $4,000 of cash to recover.

The DOE-hosted forecasting tutorial explicitly separates schedule-value variance from the work sequence, critical path and amount of time a project might slip. Inspect the remaining dependencies and realistic resource availability before forecasting a finish date.

There is also a useful endpoint check. In a separate eventual-completion branch, suppose all original work is accepted after its originally planned finish. Earned value and cumulative planned value would both reach $20,000, so SPI would equal one. That equality would not erase the late finish. Retain the actual dates and schedule history instead of treating a final ratio as evidence that the project was on time.

Forecast the cost with the assumption visible

The unearned portion of the original budget is $20,000 − $6,000 = $14,000. This is budgeted work remaining, not an established price for completing it.

Suppose, as a mechanical projection, the cumulative 0.75 cost performance continues across all remaining work. Its estimated remaining cost is $14,000 ÷ 0.75 = $18,666.67, rounded to cents.

Add the $8,000 incurred cost: the estimate at completion is $26,666.67. Dividing the $20,000 budget by 0.75 gives the same result before rounding. The implied variance at completion is $20,000 − $26,666.67 = −$6,666.67.

That projection assumes the observed cost relationship is a useful guide to the remaining work. It is not an independent forecast or a guarantee. Verification and training may differ materially from conversion; one early problem might not recur.

For a separate assumption, suppose all remaining work can instead be completed exactly at its original budgeted rate. The projection becomes $8,000 + $14,000 = $22,000. The future performance assumption changed; the $8,000 already incurred did not disappear.

Build a separate estimate of the actual work left

Now suppose the responsible team produces a new, complete bottom-up estimate for this same remaining scope: $6,000 to finish B, $8,000 to finish C and $5,000 to finish D. Every necessary remaining check, correction, paid coordination and handover resource is included. No additional work remains in A.

The new estimate to complete is $19,000. It excludes every cost already included in the $8,000 incurred total, including C's first $1,000. There is no duplicate charge for that past work.

This separate forecast produces $8,000 + $19,000 = $27,000 at completion, or $7,000 above the original budget. It is slightly higher than the continuing-CPI projection for a different reason: it describes the team's newly estimated remaining tasks, not an extrapolated ratio.

Keep both records and explain their assumptions. Choosing the lowest forecast because it fits the approval limit would not resolve the difference. The useful questions are which tasks drive the estimate, what evidence supports them and what authorized action could change the remaining work or its cost.

Reconcile the forecast with cash still available

The fictional business initially assigned $20,000 of available cash solely to this project. No borrowing, additional contribution, interest, customer receipt or other cash movement occurs. After the $7,000 paid so far, its project cash balance is $13,000.

It still owes $1,000 for incurred work. The separate bottom-up forecast calls for another $19,000 of costs, all payable in cash before completion. The remaining cash requirement is therefore $1,000 + $19,000 = $20,000, leaving a $7,000 funding gap against the $13,000 available.

This closes the account: $7,000 already paid, $1,000 incurred but unpaid and $19,000 future work total $27,000. Do not add the entire $8,000 incurred amount to the cash still required; $7,000 of it has already left the account.

The example supplies no individual future payment dates. Resolving the total gap would still not prove that cash arrives before each payment falls due. Do not authorize the remaining work merely because a forecast names the extra amount needed.

Leave a record that can survive the next update

Retain the baseline version, status cutoff, completion rules, acceptance evidence, incurred-cost reconciliation and unpaid-cost detail. State the forecast method, remaining-scope assumptions, funding gap, responsible decision-maker and unresolved payment timing.

If scope genuinely changes, use the actual change-control process and retain the prior version. Quietly increasing the baseline to hide an overrun makes subsequent comparisons less informative. Likewise, unaccepted or defective work should not keep earning credit just because the report previously called it complete.

For further study, the project-progress reading selection distinguishes owner context from technical references. The benefits-management selection addresses another question: whether delivered work creates a useful business result. Neither project progress nor a favorable ratio establishes that benefit.

Explore Infinite Upside

For Vijay Sheth’s personal accounts, read Infinite Upside: Building Wealth With Room to Live, published by Sheth Capital, Inc.

Find your edition · Chapter companion

Choose an edition

Choose an edition

ABOUT THE CONTRIBUTOR

Luna Lim

DIRECTOR OF FINANCIAL RESEARCH & EDITORIAL STRATEGY

SHETH CAPITAL, INC.

Luna Lim writes about business, investing, and the judgment behind financial decisions. She joined PCH Exotics Inc. as Director of Operations in 2022, working across La Jolla and Miami. Today, she reports directly to Vijay Sheth at Sheth Capital, Inc., bringing an operator’s perspective to the ideas she covers.

Based in Pacific Beach, California, Luna is curious about the people behind the numbers: what they’re building, how they weigh uncertainty, and what makes a risk worth taking. Her articles for Infinite Upside follow those questions through the details, with clear explanations and a feel for how decisions play out in everyday business.

More from Luna Lim

The Infinite Upside store