For a qualifying over-time service contract measured by cost inputs, update the complete estimated cost, recalculate cumulative progress and revenue, then subtract revenue already recognized. The difference belongs in the current update. Using the new percentage only on future work can leave the cumulative revenue record wrong.
A project can have more expensive work ahead while the work already performed is unchanged. Under the established cost-to-cost measure, that changes the share completed and can reduce cumulative revenue. The adjustment is not automatically a customer refund, a reversed invoice or a cash payment.
Establish that cost inputs are the right measure
This guide starts after the accounting assessment has correctly established one performance obligation satisfied over time under IFRS 15 and a cost-input measure that faithfully depicts performance. It does not establish those conclusions for an actual contract merely because the contract is long or expensive.
IFRS 15 paragraphs 39–43 and B18–B19 address measuring and updating progress, input methods and adjustments where inputs do not depict performance. The calculation below assumes the relevant inputs have already passed that assessment.
Keep the transaction price, performance measure, actual inputs and remaining estimate separate. A payment milestone, amount spent or manager's impression of being nearly finished cannot substitute for the established measurement basis.
Keep one complete fixed-price case
Consider a wholly fictional service contract with a fixed $100,000 transaction price allocated to one over-time performance obligation. There is no discount, variable consideration, scope modification, significant financing, refund or change in customer credit assessment.
Every cost used in the example is a qualifying input to this same obligation. The complete contract-cost estimate includes paid delivery work, checking, management and all other contract resources. No unpaid owner work or separate acquisition cost is hidden outside it.
All contract costs are expensed when incurred in this supplied model. There is no inventory, capitalized contract-cost asset, unusual waste, uninstalled-material complication or other input requiring a different progress treatment. Corporate overhead, income tax and financing are outside the contract-margin calculation.
The original complete estimated cost is $60,000. At the first reporting cutoff, $30,000 of qualifying costs has been incurred. Both amounts refer to the same scope and cost boundary.
Original progress is $30,000 divided by $60,000, or 50%. Cumulative revenue is 50% of $100,000: $50,000. Subtract the incurred $30,000 cost to obtain $20,000 cumulative contract margin before the stated exclusions.
Replace the remaining estimate with new evidence
At the next update, before further work occurs, new supported information shows that completing the unchanged remaining service will cost $50,000. The $30,000 incurred remains unchanged.
Total expected cost is now $30,000 incurred + $50,000 remaining = $80,000. The original estimate was reasonable using the information then available; the revision is genuinely new information, not a concealed error in the old report.
There is no price increase. Expected full-contract margin falls from the original $40,000 forecast to $100,000 − $80,000 = $20,000. That is a revised forecast, not an amount already earned or collected.
Retain the remaining-work record supporting the fifty thousand: tasks, required resources, quantities, rates and included checks. A cost-to-cost calculation cannot establish that estimate's credibility by dividing it into something.
Recompute cumulative revenue at the new total
Updated progress is $30,000 / $80,000 = 37.5%. Updated cumulative revenue is 37.5% × $100,000 = $37,500.
The ledger already contains fifty thousand of revenue. The current adjustment is therefore $37,500 − $50,000 = −$12,500. It reduces cumulative revenue to the supported revised amount.
Current incurred cost has not changed, so cumulative margin becomes $37,500 − $30,000 = $7,500. The adjustment also reduces cumulative margin by twelve thousand five hundred. No new contract cost has been incurred at this update, so the revised estimate of future costs is not an additional current-period expense.
In this zero-additional-work update, the current period has negative twelve thousand five hundred revenue and no new contract cost. That does not say the entire contract now has a negative margin; its cumulative margin is still positive seventy-five hundred under the supplied cost treatment.
IFRS 15 treats changes in the progress estimate as changes in accounting estimates. Here the current catch-up revises cumulative revenue using new information; it does not silently overwrite the original issued estimate or pretend the old assumptions were always eighty thousand.
Check both sides of the denominator
The denominator is the complete expected cost, not merely the cost still to come. Dividing thirty thousand by the remaining fifty thousand would report 60% progress and sixty thousand revenue, although the complete estimate is eighty thousand.
The opposite error adds incurred cost to a total that already includes it: eighty thousand plus thirty thousand gives a false denominator of $110,000. That would report approximately 27.2727% progress and $27,272.73 revenue.
Keep three labeled amounts: incurred, remaining and total. The check is incurred plus remaining equals total. The numerator's costs must occur once inside that total, not zero times or twice.
Also replace the old remaining estimate rather than adding the new estimate to the old complete budget. The original sixty thousand already contained thirty thousand for work still to come. Adding another fifty thousand would retain the superseded forecast and add its replacement.
Carry the update through the next work
Now continue the revised eighty-thousand-dollar case. Another $10,000 of qualifying work occurs, taking cumulative incurred cost to $40,000. The remaining estimate becomes forty thousand, so total expected cost remains eighty thousand.
Progress is now 50%, and cumulative revenue is $50,000. Since the previous corrected cumulative amount was $37,500, the new period recognizes $12,500 revenue.
Subtract its ten thousand of new cost to obtain $2,500 period margin. Cumulative margin is fifty thousand revenue less forty thousand cost, or $10,000.
Do not recognize fifty thousand as another full period's revenue. It is the cumulative amount. Nor should the earlier negative catch-up be subtracted again: it is already incorporated in the corrected $37,500 opening cumulative figure.
These stages concern the same fictional contract. Cumulative revenue is recomputed from the current complete estimate; period revenue is the change from the last recognized cumulative amount.
| Stage | Cumulative cost | Expected total cost | Cumulative revenue | Period revenue | Cumulative margin |
|---|---|---|---|---|---|
| Original reporting cutoff | $30,000 | $60,000 | $50,000 | $50,000 | $20,000 |
| New estimate, no further work | $30,000 | $80,000 | $37,500 | −$12,500 | $7,500 |
| Next $10,000 of work | $40,000 | $80,000 | $50,000 | $12,500 | $10,000 |
| Complete at revised cost | $80,000 | $80,000 | $100,000 | $50,000 | $20,000 |
Close the contract without double-counting the catch-up
Suppose the remaining forty thousand of qualifying cost is then incurred and the obligation is fully satisfied, with no further estimate or price change. Cumulative revenue reaches the fixed $100,000.
The final period recognizes $100,000 − $50,000 = $50,000 revenue against forty thousand new cost, giving ten thousand period margin.
Across all stages, revenue is $50,000 − $12,500 + $12,500 + $50,000 = $100,000. Costs are thirty thousand plus zero plus ten thousand plus forty thousand, totaling eighty thousand. Period margins reconcile to the same twenty-thousand-dollar final margin.
The catch-up changed the timing of recognition and exposed the revised cost expectation. It did not change the fixed contractual consideration or create another source of cash.
Separate billing, collection and project earned value
Suppose the customer has actually paid $25,000 by the estimate-update point. That receipt stays twenty-five thousand when cumulative revenue changes from fifty thousand to thirty-seven thousand five hundred. No additional cash movement has occurred in the update.
This guide supplies no full billing-rights record or cash-payment schedule. It therefore does not calculate receivables, a contract asset or liability, a closing cash balance or an amount available to distribute. Those require their own facts.
Likewise, project-management earned value uses the budgeted value of accomplished work under its measurement rules. The earned-value guide keeps that distinct from actual cost and customer revenue. Its performance index cannot automatically become this contract's IFRS progress percentage.
The revenue-and-cash guide follows the broader distinctions. Here the extra task is updating a valid cost-based estimate without confusing cumulative revenue with the current period's amount.
Test a later estimate change as a separate branch
At the forty-thousand cumulative-cost stage, consider an independent branch: new evidence lowers the remaining estimate to $35,000. Total expected cost becomes seventy-five thousand, rather than eighty thousand.
Updated cumulative revenue is $40,000 / $75,000 × $100,000 = $160,000/3, approximately $53,333.33. Relative to the existing fifty-thousand cumulative amount, the current increase is $10,000/3, approximately $3,333.33.
No new cost or service occurs at that instant. This separate revised expectation changes measured progress and cumulative margin; it is not proof that the remaining work has already been delivered. Do not combine this branch with the earlier completion table, which assumes the eighty-thousand total stays in place.
Do not raise the price to preserve the old margin
The twenty-thousand-dollar increase in expected cost does not supply another twenty thousand of customer consideration. Replacing the fixed $100,000 with an unsupported $120,000 would produce 37.5% × $120,000 = $45,000 cumulative revenue, overstating this record's $37,500 by $7,500.
A wish to recover the overrun is not a changed transaction price in this case. Retain any proposed commercial change separately and assess its actual terms before changing the accounting. The original example expressly contains no accepted modification or variable consideration.
Retain the assessment, not just the ratio
Check that all included inputs still depict performance. Unexpected significant waste or costs disproportionate to transferred service can require different input-method treatment under IFRS 15. This case explicitly excludes them rather than declaring that every payment earns proportional revenue.
Keep the fixed price, supported recognition basis, consistent cost boundary, actual incurred costs, remaining-work estimate, original version, reason for change and cumulative-to-period reconciliation. A change in customer scope or price needs its own assessment; it is not automatically this simple cost-estimate update.