Use three-point project estimates to expose the assumptions behind uncertain activity durations, not to manufacture confidence in a promised finish. Record the optimistic, most likely and pessimistic cases, state the model connecting them, then examine the whole dependency network, resource constraints and relationships between risks.
A weighted average can be calculated correctly and still answer the wrong question. The average of a task is not its guaranteed duration. The longest route made from average tasks is not necessarily the average finish of a project with parallel work.
Write what the three points actually mean
Define the complete activity and its usable finish. Include required checking and handover. Fix the resources and working calendar assumed by the estimator before asking for durations.
Then identify what each point represents. Does optimistic mean a plausible favorable case, a theoretical minimum or a particular percentile? Does pessimistic include a named disruption or exclude it? Two estimators can supply the same numbers while describing different uncertainty.
Keep the basis beside the estimates: comparable work, supplier evidence, unresolved design decisions or informed judgment. Identify important risks that the range does not cover. A narrow range copied from a desired deadline is not independent evidence for that deadline.
Waiting time and active labor are also different. An eight-day supplier lead time does not automatically consume eight full days of staff work. Preserve the resource and cost boundaries instead of multiplying every duration by a payroll rate.
Calculate an average under a named model
PMI's public schedule-risk discussion distinguishes the three-point inputs from the distribution assumption. It gives the triangular mean as the three inputs divided by three, and the traditional beta-based PERT approximation as optimistic plus four times most likely plus pessimistic, divided by six.
For a separate original teaching activity, suppose the judgments are two working days optimistic, four most likely and eight pessimistic. The traditional weighted calculation is (2 + 4 × 4 + 8) ÷ 6 = 26 ÷ 6, about 4.33 working days.
Under a triangular model using those same bounds and mode, the mean is (2 + 4 + 8) ÷ 3 = 14 ÷ 3, about 4.67 days. The difference is one-third of a working day. No actual activity became faster when the formula changed.
The four-times weighting does not mean there is a four-in-six probability that the activity lasts exactly four days. Nor have the three judgments alone established a 95% completion date. The probability statement needs an appropriate model and supported inputs.
Keep the unrounded fractions in subsequent calculations where practical. A display showing 4.3 days should not silently change the underlying model to a fixed 4.3-day task with no uncertainty.
A complete original parallel project
Now use an independent, entirely fictional project to examine the network question. This is a separate finite probability model, not a distribution inferred from the earlier two-four-eight judgments.
Two activities, A and B, start at time zero with separate qualified, paid resources. Both must finish before final acceptance C begins. C always takes one working day, including the complete check and handover.
Each of A and B takes either two days with probability one-half or eight days with probability one-half. For the initial case, their durations are independent. All four joint combinations therefore have probability one-quarter.
The model includes all necessary work, immediate handoffs, one shared working-day calendar and no holidays, resource conflicts, rework or other delays. It supplies fictional planning probabilities, not observations from an actual project or evidence that real durations cannot fall outside these values.
Scroll across all four joint outcomes. Final acceptance waits for the later predecessor.
| A duration | B duration | Joint probability | Project finish: max(A, B) + 1 |
|---|---|---|---|
| 2 days | 2 days | 25% | 3 days |
| 2 days | 8 days | 25% | 9 days |
| 8 days | 2 days | 25% | 9 days |
| 8 days | 8 days | 25% | 9 days |
Do not find the average finish by averaging first
A's mean duration is 2 × 50% + 8 × 50% = 5 days. B has the same mean. Replacing both activities with five-day constants gives a six-day project: max(5, 5) plus one.
But the actual supplied project outcomes are three days with probability 25% and nine days with probability 75%. Their expected finish is 3 × 25% + 9 × 75% = 7.5 days.
The six-day calculation understates that modeled expected finish by 1.5 days. The final activity must wait for whichever predecessor finishes later. Averaging the predecessors before taking their maximum loses that relationship.
Even 7.5 days is not an outcome this finite model ever produces. It is a probability-weighted mean of three and nine, not a date that occurs most often or a buffer already added to a commitment.
This is an original exact illustration of a merge-point problem discussed in PMI's schedule-risk article. No simulation was needed for four outcomes, and no results from the source's project examples are being reused.
Answer the deadline question directly
Under the independent finite model, completion by six days has probability 25%. Completion by eight days is also 25%, because none of the nine-day outcomes has finished. Completion by nine days is 100% within the model.
The smallest deadline meeting a target of at least 95% under these supplied outcomes is nine days. That modeled 100% is not a real-world guarantee. It depends on the deliberately exhaustive two-duration assumptions and the exclusion of other disruptions.
A deadline between the outcomes does not create an intermediate success probability. Adding two days to the six-day average-task schedule produces eight, yet still covers only one-quarter of this model. A generic percentage buffer would need its own justification.
For the dependency mechanics themselves, use the critical-path guide. Its deterministic example explicitly supplies no statistical confidence estimate. Adding a probability label afterward would change the claim without adding the necessary evidence.
Marginal ranges do not tell you how risks move together
Retain each activity's two-or-eight-day distribution, but change the joint relationship in a separate branch. Suppose A and B are always short together or long together, each joint outcome having probability one-half.
Each activity still averages five days. The project now finishes in three days half the time and nine days half the time, so its mean is six days. The probability of completion by six is 50%.
In a different branch, exactly one activity is short while the other is long, with the two arrangements equally likely. Each activity again averages five days, yet the project always finishes at nine days.
The same individual distributions therefore produce project means of six, 7.5 or nine days, depending on the supplied joint relationship. The three-point estimates for individual tasks cannot establish which relationship applies.
In real work, shared suppliers, weather, access or design decisions may connect durations. Investigate the actual relationships. Do not assume independence merely because two activities have separate spreadsheet rows, or import one of these extreme fictional relationships as a forecast.
Check a confidence label at the merge
In another independent illustration, suppose each of two required predecessor paths has a genuinely supported 90% probability of meeting the same handoff deadline. This replaces the earlier duration model; it is not a new interpretation of its fifty-fifty activities.
If the two handoff events are independent, the probability both meet that deadline is 0.9 × 0.9, or 81%. Calling the merged handoff 90% confident would ignore the requirement that both succeed.
Without a supported dependence assumption, the two marginal probabilities alone permit a joint success probability from 80% to 90%. The upper limit cannot exceed either individual 90%; the lower follows because the combined failure probability cannot exceed 10% plus 10%. These are mathematical bounds, not a selected project forecast. The relationship still needs evidence.
Connect the duration risk to a complete cost scope
Return to the initial independent model. Suppose the complete fixed project fee is $2,500, covering every activity's paid work and all other fixed project charges. A separate complete equipment-and-space carrying charge is $200 per elapsed working day until final acceptance, including that day's charge.
There are no other project costs, receipts or payment adjustments in this bounded cash case. All project payments occur before any customer receipt, and no credit facility or additional contribution has been arranged.
A three-day finish costs $2,500 + 3 × $200 = $3,100. A nine-day finish costs $4,300. Expected cost is 25% × $3,100 + 75% × $4,300 = $4,000.
The business has $4,200 actually available for the project after other obligations. Expected cost leaves $200, but the nine-day outcome requires another $100. That outcome has 75% probability in this fictional model. Funding the average has not funded all modeled requirements.
Using the six-day average-task schedule would instead budget $3,700, understating the modeled expected cost by $300 and the long-outcome cost by $600. Neither missing amount is supplied by the model's arithmetic.
The GAO Schedule Assessment Guide's overview connects credible scheduling with the cost consequences of delay. Its federal-program context supplies no universal contingency percentage for this small-business case.
Change the final acceptance duration
For a separate fictional branch of the initial independent A/B model, keep each predecessor at two or eight days with the same independent half probabilities. Change the final acceptance activity from one fixed day to two fixed working days, with qualified resources and no other work or delay omitted. This is a different supplied scope, not a claim that a real check can be extended without cost or capacity consequences.
When both predecessors finish in two days, the project now finishes in four days, with probability 25%. In the other three outcomes, it finishes in ten days, with probability 75%. Expected finish is 0.25 × 4 + 0.75 × 10 = 8.5 days. The earlier one-day-acceptance model had a 7.5-day expected finish.
Under this new model, completion by nine days has probability only 25%, rather than the original model's 100%. A deadline of ten days reaches 100% within the stipulated outcomes. Neither result is a real-world guarantee, and a model with additional delay possibilities could differ.
If the separate cash assumptions are also kept—$2,500 fixed and $200 per elapsed working day—the four-day and ten-day costs are $3,300 and $4,500. Their expected cost is $4,200. That equals the supplied available cash, yet the ten-day outcome exceeds it by $300 and occurs with probability 75% in this model. This assumes the same complete fixed fee covers the longer acceptance work; actual staffing, payment dates and commitments require evidence.
Price a stipulated mitigation before counting savings
Return to the initial independent A/B duration model and its one-day acceptance, $2,500 complete fixed fee and $200 daily carrying charge. For a separate hypothetical proposal, assume paying $200 extra guarantees that A's long outcome becomes six days instead of eight while A's short outcome remains two; B's two-or-eight-day distribution and independence are unchanged. Assume the extra payment buys complete qualified resources and creates no other changes. These are supplied fictional effects, not an estimate of a real mitigation.
The four equally likely A/B outcomes now finish in 3, 7, 9 and 9 days, including the one-day acceptance. Their mean is seven days, compared with 7.5 in the original model. At $2,700 fixed including the added payment plus $200 per day, the respective costs are $3,300, $4,100, $4,500 and $4,500. Expected cost is $4,100, $100 more than the original $4,000.
With the same $4,200 available, the two nine-day outcomes each leave a $300 funding shortfall, and together have 50% modeled probability. The original long outcome had a $100 shortfall with 75% probability. The proposed mitigation lowers the modeled chance of a shortfall but raises both expected cost and the shortfall in the remaining long outcomes. It has not automatically made the funding plan adequate.
A decision needs the credible cost and effectiveness of the actual measure, any changes to dependence, contractual obligations and the timing of payments. These four outcomes and the claimed guarantee are deliberately stipulated; neither the schedule-risk reference nor this example establishes that real project work can be accelerated for $200. Compare the whole revised cost and risk with available funds before committing.
Leave the assumptions with the date
Keep the activity scope, resources, calendar, three-point meanings, source evidence, distribution assumptions, dependence assumptions and included risk events with the forecast. Preserve the original version when evidence changes.
Report a deterministic finish, an expected finish and a selected probability-based date as different results. Identify remaining exclusions and the funding needed for the outcome the business actually intends to support.
A larger project may need a properly designed schedule-risk analysis rather than a short table. More simulated runs do not cure missing work, an implausible distribution or a shared risk modeled as independent. Verify the model before treating its smooth curve as confidence.