INFINITE UPSIDE

From dependency list to feasible finish

How do I calculate a project critical path?

The longest chain matters, but the people needed to carry it out still have to be available.

Calculate a project's critical path by listing the work, linking each activity to what must finish before it starts, and finding the longest connected route to completion. Work forward to find the earliest times, then backward to find the latest times consistent with that finish. The difference exposes schedule flexibility, called float. Check people, equipment and calendars before treating the result as a workable promise.

The shortest task can hold up the whole project. The busiest person can be working on something that does not move its finish date. A useful schedule explains those differences instead of coloring the most conspicuous activities red.

Define a finish that someone can use

Start with a specific result and a completion condition. “Install the equipment” might leave out verification, training or acceptance. If those are necessary before the next person can use it, put them in the network.

Give each activity a duration and a clear predecessor. A finish-to-start relationship means the successor cannot begin until its predecessor is finished. Do not add that link merely because two tasks appear next to each other on a checklist.

The PMI paper on basic critical-path calculations explains forward and backward passes and distinguishes total float from free float. The example below uses original activities and numbers, with an elapsed working-time clock beginning at zero.

Keep units consistent. Two working days are not necessarily forty-eight elapsed hours. Our case uses one common working-day calendar, no holidays or interruptions, and immediate handoffs at activity boundaries. It is a simplified scheduling exercise, not a dated commitment.

An original six-activity project

A fictional workshop is preparing a small internal packing station. Its bounded project includes these six activities. Every listed duration includes the complete work and necessary checks for that activity, rather than only the most visible installation action.

  • A: confirm the station specification. One working day; no predecessor.
  • B: obtain the specified kit. Three working days; A must finish.
  • C: prepare the work area. Two working days; A must finish.
  • D: install and verify the station. Two working days; both B and C must finish.
  • E: complete the staff training. Two working days; C must finish. In this fictional design, training uses a separate training setup and does not require D.
  • F: complete final acceptance and handover. One working day; both D and E must finish.

The original case has separate qualified, paid resources for work that overlaps. The kit is available on the stated lead time; the work area and training setup are available when required. There are no other competing duties, resource shortages, omitted approvals or outstanding work beyond this complete project scope.

Those are supplied fictional assumptions, not facts established about an actual workshop. No funding amount or commercial outcome is supplied. A feasible timing calculation would still not establish that a real project is affordable or authorized.

Work forward to find the earliest finish

Set A's earliest start at zero. It takes one day, so it finishes at time one. B and C can both begin then: B finishes at four, while C finishes at three.

D needs both. Its earliest start is the later predecessor finish, max(4, 3) = 4. Its two days take it to six. E needs only C and runs from three to five.

F waits for both D and E, so it begins at max(6, 5) = 6 and finishes at seven. The earliest modeled completion is therefore seven working days.

Adding all six durations gives eleven days of activity duration. That is not the project's elapsed duration because some activities overlap. It is also not a labor-hours estimate: B includes obtaining a kit, and the case does not specify how much of its lead time requires active labor.

Work backward to find the latest times

Use seven as the required finish for this backward pass. F must start by six. D and E must therefore each finish by six; with two days apiece, their latest starts are both four.

B must finish by D's latest start, four, and can start no later than one. C feeds both D and E. It must finish by the earlier of their latest starts: min(4, 4) = 4. Its latest start is two.

A feeds B and C, whose latest starts are one and two. A must finish by one, so its latest start remains zero.

Scroll across to compare early and late times. All entries are elapsed working-day positions on the same clock.

ActivityEarly startEarly finishLate startLate finishTotal float
A01010
B14140
C13241
D46460
E35461
F67670

Subtract early start from late start to find total float. C and E each have one day. A, B, D and F have none relative to the seven-day finish.

The connected route A → B → D → F totals 1 + 3 + 2 + 1 = 7. The other routes, A → C → D → F and A → C → E → F, each total six. Under these unconstrained assumptions, the seven-day route is the critical path.

One day of float is not two separate gifts

C has one day of total float, but zero free float. E is scheduled to start immediately when C finishes at three. Delaying C delays that successor's early start even when the project finish remains unchanged.

Suppose C starts at two instead of one and finishes at four. D still starts at four, but E shifts to four through six. F can still start at six and the project still finishes at seven.

Now E has used the flexibility that appeared in its original row. If E also takes an extra day, it finishes at seven, F runs from seven to eight, and the project finishes a day later.

You cannot independently spend C's one day and E's one day as though the path contained two days of spare time. Recalculate the connected work whenever a delay consumes float. A row in a table describes its relationship to the rest of that particular schedule, not a personal entitlement to delay.

Shortening a critical task can create new critical paths

In a separate hypothetical branch, B's complete lead time falls from three days to two, with every other condition unchanged. This is an assumed capability, not a confirmed supplier offer or permission to skip receiving checks.

B now finishes at three, alongside C. D runs from three to five; E still runs from three to five; F runs from five to six. The project improves from seven days to six.

All three routes now total six. There are several critical branches, so watching only the old A–B–D–F route would miss work that has become equally important to completion.

Shorten B again, from two days to one, and it finishes at two. D still waits for C until three, E still finishes at five, and the project still finishes at six. Another day removed from B provides no further reduction in this modeled finish.

That is a reason to calculate the whole network before paying to accelerate one task. An attractive local improvement can stop affecting the promised date. The example supplies no expedite price or additional funding and establishes no monetary return from finishing earlier.

A shared person can change the answer

Return to the original three-day B. In an independent resource branch, D and E require the same qualified specialist for their complete two-day activities. Neither task can be interrupted, and the specialist cannot perform both at once. All other assumptions remain unchanged.

The original table overlaps D and E from four to five. That schedule is now infeasible.

If the specialist does D first, D runs from four to six and E from six to eight. F then runs from eight to nine. The finish is nine days.

If the specialist does E first, E runs from three to five. D is ready at four but waits until five, then runs through seven. F runs from seven to eight. This sequence finishes in eight days.

For this small case, eight is also the earliest feasible finish: the specialist cannot start either activity before three, needs four nonoverlapping days to complete both, and F needs another day afterward. The E-first sequence achieves that lower bound. This is a proof for the stated two-task conflict, not a general scheduling optimizer.

The GAO Schedule Assessment Guide discusses how resource availability, calendars and constraints can affect critical paths and float. Our simple table deliberately excluded those complications at first. A real schedule must restore the relevant ones before anyone relies on its date.

Keep the working schedule and the promise connected

  1. Name the usable finish. Include verification, acceptance and handover where required.
  2. Check the connections. Ask why each predecessor is necessary and whether any necessary link is missing.
  3. Reconstruct the timing. Use consistent calendars and complete durations; preserve the original assumptions.
  4. Check resource conflicts. Name the actual people, equipment and access needed during overlapping activities.
  5. Track consumed flexibility. Update the whole network after a changed duration, start or dependency.
  6. Authorize the revision. Keep the current feasible forecast separate from the date already promised, and resolve any gap.

A calculated seven-day finish is not a probability of finishing in seven days. This deterministic example contains no duration distributions or statistical confidence estimate. It also has no explicit contingency allowance. Unknown kit availability or a failed acceptance check would require new evidence and a revised forecast.

The development-stage discussion addresses a different boundary: whether the earlier opening is useful and funded on its own. The project-progress reading selection offers further study directions. Neither turns a calculated date into evidence that all project obligations are ready.

Explore Infinite Upside

For Vijay Sheth’s personal accounts, read Infinite Upside: Building Wealth With Room to Live, published by Sheth Capital, Inc.

Find your edition · Chapter companion

Choose an edition

Choose an edition

ABOUT THE CONTRIBUTOR

Luna Lim

DIRECTOR OF FINANCIAL RESEARCH & EDITORIAL STRATEGY

SHETH CAPITAL, INC.

Luna Lim writes about business, investing, and the judgment behind financial decisions. She joined PCH Exotics Inc. as Director of Operations in 2022, working across La Jolla and Miami. Today, she reports directly to Vijay Sheth at Sheth Capital, Inc., bringing an operator’s perspective to the ideas she covers.

Based in Pacific Beach, California, Luna is curious about the people behind the numbers: what they’re building, how they weigh uncertainty, and what makes a risk worth taking. Her articles for Infinite Upside follow those questions through the details, with clear explanations and a feel for how decisions play out in everyday business.

More from Luna Lim

The Infinite Upside store