How to review a construction change order

A change can improve a project. Follow the price, timing and work around it before you agree.

A change order is easy to recognize when it arrives as a document with a number at the top. It is less easy to recognize when the conversation starts with, “While you’re here, could we move that door?”

Before agreeing to a construction change order, compare the proposed work with the current contract and drawings, identify what is being added or removed, and follow its effect on price, payment timing and the schedule. Check the proposed credit for work no longer needed, find out who can authorize the change, and keep unresolved questions visible. A $12,000 price is only one part of the decision if the change also affects permits, other trades or the date the business expects to open.

The aim is not to make every adjustment adversarial. Buildings are assembled in the real world, which is famous for refusing to remain exactly as drawn. A useful change process lets the owner and contractor solve a problem without asking either one to remember an incomplete conversation six months later.

Start with the work already agreed

Imagine a fictional business converting an existing space into a small studio. Its construction contract is $420,000, and the owner has set aside a separate $30,000 contingency for changes and other project surprises. The owner’s total construction allowance is therefore $450,000 before any expenses the example has not included, such as financing or opening inventory.

During construction, the owner asks about moving a planned interior door. The contractor proposes a $12,000 change that includes revising the partition, installing a different door assembly and adjusting electrical work affected by the move. Before deciding whether $12,000 is reasonable, both sides need to know what the existing agreement already requires.

Find the relevant contract, scope and current drawing. Which door, partition and electrical work were included? Which drawing revision did the contractor price? Is the proposed door replacing an item already in the contract, or is it additional? The answer matters because an attractive-looking list of new work can still omit a credit for work that will no longer be performed.

That does not mean the credit equals the original retail price of every removed item. Perhaps a component was already ordered, fabrication began, or a supplier charges a return fee. Ask for the proposal’s assumptions and supporting detail. A useful comparison shows the added work, the work removed, any recoverable credit, and costs that remain because they have actually been incurred or cannot be avoided under the relevant agreements.

One U.S. General Services Administration contract clause requires certain federal construction adjustment proposals to identify, where applicable, direct costs, markups and changes to completion time, including added and deleted work. That clause applies in its own federal-contract setting; a private studio project is governed by its own agreement and applicable law. The underlying habit—make the changes visible on both sides of the ledger—is useful for the fictional owner’s review.

Follow the price without counting it twice

Suppose the contractor’s $12,000 proposal is a net amount after accounting for the work removed. If approved under the applicable agreement, the contract price would increase from $420,000 to $432,000. The owner’s $30,000 contingency would have $18,000 remaining for other uses, assuming no other changes or contingency expenditures.

Now add two separate items. A previously approved change added $7,000. Another approved change reduced the price by $2,000. The two approved changes total $5,000, bringing the contract to $425,000 and leaving $25,000 of contingency under these assumptions. If the $12,000 door change is also approved, the net change would be $12,000 + $7,000 − $2,000 = $17,000. The revised construction contract would be $437,000, and $13,000 of the original $30,000 contingency would remain, if no other contingency costs exist.

Then an additional $9,000 proposal arrives for a different issue. It has not been approved. Keep it visible as pending rather than adding it to the signed contract price. If both the door and the additional proposal were approved at those amounts, the total change would rise to $26,000, the contract would become $446,000, and $4,000 of the original contingency would remain under the same narrow assumptions.

The currently approved changes total $5,000; the door and the additional $9,000 proposal remain pending. If both are approved at the quoted amounts, total changes would be $26,000. The approved amount, pending proposals and total possible exposure answer different questions. A lender, owner or project manager needs to know all three. A column labeled “remaining contingency” is not much help if it quietly treats pending work as either certainly approved or entirely nonexistent.

For this illustration, the $12,000 door price already includes its net credit. Subtracting that same credit again would understate the revised price. Likewise, a $2,000 reduction from a different approved change should not be treated as money the owner has already received unless the payment records actually show that adjustment. Contract value, invoices due and cash paid are related records, not interchangeable ones.

What still has to fit inside the contingency?

After the owner records approved changes and shows pending proposals separately, the remaining balance still has a job: covering risks that have not yet become priced changes. An older renovation may conceal damaged framing; a project on a new site may face different ground or utility questions. List the material uncertainties that remain, their possible cost ranges, when the team expects to learn more and what work might reduce the uncertainty.

Keep that risk view separate from the change log. A possible $20,000 repair is not an approved $20,000 contract increase. It can still matter when deciding whether the remaining contingency is enough. Avoid adding the same exposure as both a pending proposal and a separate risk. Also consider related effects: one delay might increase both temporary facilities and financing costs, even if only one appears on the contractor’s proposal.

The Government Accountability Office’s cost-estimating guide discusses documenting assumptions, examining risk and updating estimates as facts change. It is a public-sector framework, not a prescribed reserve percentage for this studio. A smaller contingency after a credible issue is priced can be more useful than an untouched balance that no one has compared with the risks still ahead.

What does the proposal actually buy?

A useful review does not require the owner to become the electrician, architect and estimator before lunch. It does require enough description to understand the decision. Ask what work is included, what is excluded, which drawing or specification controls, and whether the proposed price covers the related subcontractors, materials, markups and disposal. If an inspection, design revision or permit fee may be required, identify who is responsible and whether its cost is included or still unknown.

Look for the point where one trade’s work becomes another’s problem. Moving the door may require a relocated switch. A revised switch location may affect a wall finish. The wall finish may have already been ordered. A proposal can be technically correct about the door and still leave the owner surprised by the surrounding work if those boundaries remain unclear.

Apply the same scrutiny to deleted work. If the original door remains on the job and will be used elsewhere, say so. If the supplier will accept a return for a fee, record whether the quoted credit is an estimate or confirmed. If completed work produces no credit, ask what was done and why it cannot be reused. The aim is to understand the adjustment, not demand a perfect refund.

A vague line reading “miscellaneous changes: $12,000” is difficult to evaluate and even harder to reconcile later. A list of a hundred tiny numbers is not automatically better if no one can explain what outcome they produce. Ask for the level of detail that lets the parties identify the work, evaluate the significant costs and resolve the open assumptions.

Schedule impact is not the same as task duration

A change may take four days of work without moving the project’s final date by four days. It might fit inside available time while another task continues. It might also hold up several dependent trades and delay the opening by more than the time spent on the immediate change. The project schedule, not the number on the proposal alone, determines what needs to be examined.

For a deliberately simple illustration, suppose the door decision must be made before a four-day installation can begin. In the current schedule, that work has three working days of available float before it affects the planned finish, assuming all the stated dependencies and other work remain unchanged. If approval arrives one working day later than planned, and the rest of the sequence does not change, the task could use one day of float without moving the finish.

If approval instead arrives four working days late, the task would use the three available days and exceed that float by one working day. Under those simplified assumptions, the planned finish would move by one working day—not four. If another delayed task also controls completion, the answer could change. So could the answer if the proposed sequence, resource availability or approved schedule changes.

Ask the contractor to show the affected tasks and the basis for any requested time adjustment. Does the proposal refer to working days or calendar days? Does it assume a particular approval date, supplier lead time or inspection? Is the estimated impact on an intermediate milestone or the final completion date? A schedule can look reassuringly precise while leaving its most important assumption in someone’s head.

The Government Accountability Office’s review of federal construction contract changes describes how owners and contractors can experience a change process on different timelines, partly because a change may affect cost and schedule before the government’s formal process starts. It examines federal agencies, not every private project, but it illustrates why the date a problem is noticed and the date a modification is approved are worth recording separately.

For a deeper look at how linked activities determine a finish date, work through the critical-path example. Float is not an invitation to promise away time casually; it is a schedule result that can change as the project changes.

Who can make the decision?

Before work begins, find the approval procedure in the actual agreement. It may identify who can request a change, who can approve price and time, what form the approval takes and how a disagreement is handled. A site conversation with the person who noticed the problem is useful information, but the parties should not assume that person can amend the agreement.

That distinction protects the contractor as well as the owner. A crew may receive an instruction that sounds urgent, while the person authorized to approve the cost has not seen the price. The contractor may need to preserve evidence of an issue or follow a notice procedure before a full estimate is possible. The right sequence depends on the contract and circumstances, including any immediate safety obligations.

If the work cannot wait for a complete price, identify what is known, what remains to be priced, who can authorize the next step and when the parties expect to resolve the remaining terms. Do not silently turn a preliminary estimate into a final agreed price. Equally, do not assume that the absence of a polished form makes every instruction or obligation disappear. If a dispute arises, the documents and applicable law matter.

Put the change on the payment calendar

A change in contract price does not necessarily mean an invoice for the entire amount is due today. Check the payment schedule, deposit requirements and supporting documents in the agreement. If the contractor needs to order a long-lead item, the cash may be needed before the work is installed. If a credit will appear on a later application for payment, the owner should know when to expect it.

Suppose the $12,000 door change is approved, making the studio’s net approved changes $17,000. Suppose, only for illustration, the owner expects $8,000 of additional payment this month and $9,000 later. That is a payment-timing assumption, not a new $17,000 charge on top of the revised $437,000 contract. It helps the owner plan cash while keeping the total obligation in one place.

Also ask what a shifted opening date could cost outside the construction contract. An extra month of rent, delayed customer revenue or staff scheduling may matter to the business, but those amounts should not be folded into the contractor’s price without explanation. They belong in the owner’s broader forecast, with assumptions that can be revised. Do not claim lost sales are certain simply because the schedule moved; ask what demand and recovery options the business actually expects.

Keep a record someone else can follow

A practical change log can be short. Give each item a number and description; record the drawing or scope it affects; identify whether it is requested, priced, approved, rejected or completed; list the estimated and approved price separately; note any proposed time impact; and link the supporting documents. Add the date the issue was raised and the date a decision was made.

Then reconcile the log with the contract and payment records. If change 03 is approved for $7,000, verify that it appears once in the revised contract total and that subsequent invoices use the agreed payment terms. If change 04 is a $2,000 credit, follow it until it is reflected where the agreement says it should be. If change 05 is pending, avoid giving the team the impression that it has already been authorized.

Pictures and field notes can be useful, too, when they identify what was present before the work changed. Keep the context: where the photo was taken, when, and which issue it relates to. A camera roll of 800 unlabeled wall pictures is an impressive commitment to walls, but it is less helpful when everyone is trying to identify one covered conduit.

A good answer may be a different change

The studio owner might decide the relocated door is worth the $12,000. They might keep the original location, choose a less disruptive alternative, or ask for a revised proposal that addresses an overlooked dependency. The calculation does not make the design decision for them. It makes the consequences of each choice easier to discuss.

Before making that choice, ask: what customer or operational problem does the change solve? What happens if the original work remains? Which price and schedule assumptions still need confirmation? How much contingency remains after both approved work and credible pending exposure? And who needs to agree before a crew proceeds?

A well-run change process leaves enough room for the project to improve without letting each improvement hide the next commitment. For a related look at project completion dates, see how to calculate a critical path. For a separate question about risk if work is not performed, read what a performance bond can and cannot establish.

Explore Infinite Upside

For Vijay Sheth’s personal accounts, read Infinite Upside: Building Wealth With Room to Live, published by Sheth Capital, Inc.

Find your edition · Chapter companion

ABOUT THE CONTRIBUTOR

Luna Lim

DIRECTOR OF FINANCIAL RESEARCH & EDITORIAL STRATEGY

SHETH CAPITAL, INC.

Luna Lim writes about business, investing, and the judgment behind financial decisions. She joined PCH Exotics Inc. as Director of Operations in 2022, working across La Jolla and Miami. Today, she reports directly to Vijay Sheth at Sheth Capital, Inc., bringing an operator’s perspective to the ideas she covers.

Based in Pacific Beach, California, Luna is curious about the people behind the numbers: what they’re building, how they weigh uncertainty, and what makes a risk worth taking. Her articles for Infinite Upside follow those questions through the details, with clear explanations and a feel for how decisions play out in everyday business.

More from Luna Lim

The Infinite Upside store