How do you review a construction draw request?

A request, an approval and money in the account are different milestones.

The contractor says the project is halfway done. The lender says the draw package is incomplete. The owner says the invoices have already been paid. All three may be looking at different parts of the same project.

A construction draw request is a request for funds tied to a project's documented progress and the applicable contract or financing terms. To review one, reconcile the approved budget and changes, work completed or materials eligible for payment, amounts previously paid, retainage and the current amount requested. Then identify who must approve the request and when the money will actually be available.

A private renovation, a government contract and a construction loan do not share one universal payment formula. Follow the documents and the trail from work to payment; a requested draw is not money already received.

Start with the budget that is actually approved

A project may begin with a construction contract, a schedule of values, a lender's budget and a payment schedule. Those documents can serve different purposes. The contract describes the parties' obligations; the schedule of values allocates amounts to work categories; the lender's budget may also include financing costs, reserves, fees or owner-paid items outside the contractor's price. They should be reconciled, not assumed to be identical.

Find the current signed contract and any approved amendments or change orders. Keep pending proposed changes separate from changes formally approved under the contract. A contractor may have performed additional work, but whether and when that work is payable depends on the agreement, evidence and applicable process. A spreadsheet that adds every proposal to the contract amount does not establish approval.

For each budget category, identify its approved value, cumulative work claimed, materials included where permitted, prior approved amounts and the balance remaining. Also record what evidence supports the current request: invoices, delivery records, progress reports, inspection documents or other materials required by the agreement. The right package depends on the project and its funder.

The Federal Acquisition Regulation's discussion of construction progress payments illustrates that retainage can be governed by a contract-specific approval process in federal procurement. It does not set the rules for every private construction loan or every state. Use the actual project documents and applicable law rather than importing a government rule into a different deal.

A progress payment in practice

Imagine an owner and contractor agreed to a $400,000 construction contract. One change order for $20,000 has been approved, making the revised contract amount $420,000. A separate proposed $8,000 change remains under review and is not included in the approved amount for this example.

At the current application, assume the contractor documents $210,000 of cumulative eligible work completed, including the approved change work where applicable. The reviewers accept that amount for this simplified calculation. The $210,000 is cumulative from the start of the contract, not an additional amount completed only this month.

Assume the contract calls for 10% retainage on that cumulative eligible work and that no retainage has yet been released. Ten percent of $210,000 is $21,000. The cumulative amount available for payment after that assumed retainage is $210,000 − $21,000 = $189,000.

If $135,000 has already been paid and properly credited against that same cumulative amount, the current payment request is $189,000 − $135,000 = $54,000. The arithmetic is deliberately simple: it assumes no prior overpayment, taxes, stored-material adjustments, other offsets or disputed amounts. The retainage percentage and its treatment are fictional terms, not a universal rate.

The remaining approved contract value after the claimed cumulative work is $420,000 − $210,000 = $210,000. That is not necessarily the same as cash needed to finish the whole project: the owner may have separate costs, pending changes or other obligations, and the amount needed to complete the contractor's work may differ from the remaining contract balance.

Cumulative is the word to underline

A progress application often shows work completed through a date and then subtracts earlier payments. If a reviewer treats the full cumulative total as this month's new work, the same work can be paid twice. If the reviewer subtracts retainage or prior payments twice, the contractor can be underpaid. Follow the columns and identify what each amount represents before comparing totals.

Ask whether prior payments are shown gross or net of prior retainage. In the fictional example, the $135,000 is the amount already paid against the $189,000 cumulative net amount. If an actual form instead shows prior gross billings, retainage withheld separately or an earlier release, the calculation must follow that form and agreement. Reusing the example's subtraction without checking the definitions can create a convincing wrong answer.

Compare this application with the last approved one by line item. What changed in completed work? Was an earlier estimate corrected? Were materials delivered, installed or returned? Did an approved change move into a category? Each change should have an explanation that the project team can trace to the relevant records. A larger cumulative percentage is not, by itself, evidence that the corresponding work was completed.

The construction change-order guide addresses a related decision: documenting a proposed change, its cost and timing before treating it as part of the project baseline. A payment application should reflect the actual approval status, not turn a pending proposal into an approved contract revision by repetition.

What is retainage doing here?

Retainage is an amount withheld from a progress payment under the applicable arrangement, often addressed separately from the value of work completed. The agreement and relevant law determine whether it applies, how it is calculated, held and eventually released. It is not necessarily a discount on the contract price, and withholding it does not by itself prove that work is defective.

In the example, $21,000 is withheld from the cumulative eligible work. The net cumulative amount after that assumed withholding is $189,000. The contractor has received $135,000 and requests another $54,000. Keep a separate record of retainage held, any permitted release and the conditions for the balance. Do not record it as paid merely because it appears on an approved application.

Different categories or stages can have different terms. An actual contract may address retainage on stored materials, subcontractor work, substantial completion or final payment in a particular way. It may also be subject to jurisdiction-specific requirements. Ask the project professional to apply the controlling documents rather than assuming that every project withholds the same percentage until the same date.

Track retainage and the cash gap

For the contractor, retainage owed by the owner and amounts the contractor may owe subcontractors are separate records. The prime contract and each subcontract may use different terms and be subject to different requirements. Track each party, application, amount withheld, payment status and release condition; do not assume that withholding upstream automatically permits the same withholding downstream.

A practical closeout ledger also identifies who must act and what remains outstanding: an inspection, a test report, an approved final application or another item required by the agreement. Distinguish an amount approved for release from cash actually received. The federal fixed-price construction payment clause illustrates that progress-payment certification and retainage can involve specific conditions; it applies only where incorporated and applicable, not to every private or state project.

Consider a fictional contractor waiting 90 days for $50,000 of retainage and borrowing that full amount for the entire period at an assumed 8% annual simple rate, using a 365-day year and no fees. The estimated interest is $50,000 × 0.08 × 90 ÷ 365, or approximately $986. At 180 days under the same assumptions, it is about $1,973. Actual borrowing balances, rates and costs may differ. Several jobs with retainage outstanding at once can increase the cash needed before closeout, so forecast by project and expected payment date.

Inspection, approval and funding are separate events

A lender or owner may require an inspection, architect's certification, contractor documentation or other review before approving payment. The scope and significance of an inspection depend on the agreement: an inspection can support a draw decision without guaranteeing that every concealed condition, future defect or legal obligation has been resolved.

Keep distinct dates for the application, inspection, review, approval, funding request and receipt. A draw marked “approved” in one party's system may still require lender processing, an owner contribution or another condition before funds reach the account. Ask who confirms each stage and what evidence shows completion.

Suppose, only for this example, the lender agrees to fund 80% of the $54,000 current payment and the owner must contribute the remaining 20%. The lender's planned share is $43,200; the owner's is $10,800. These are assumed shares for the illustration, not a statement about how lenders generally allocate draws. The agreement may instead use a different funding sequence, reserve, approved budget allocation or condition.

If the owner has $10,800 ready but the lender has not released its share, the full $54,000 is not yet available from these two sources. Conversely, a lender's approval does not establish that the owner has contributed the required share. Reconcile the actual receipts and payments before calling the application funded or the contractor paid.

Mobilization before permanent work

A payment application can include work that happens before anything permanent is built: moving equipment, setting up temporary facilities or arranging site access. The label “mobilization” does not by itself establish what is payable. Compare the line with the contract, the schedule of values and the evidence of the work or cost claimed. Check whether the same trucking, rental or setup cost also appears on another line.

For example, suppose a contract allows eligible, documented mobilization costs up to $50,000 and applies 10% retainage. If $36,000 of supported costs is approved, retainage is $3,600 and the amount payable on that line is $32,400 before other adjustments. The remaining $14,000 of the cap is not automatically due: it is room under the agreed limit, not proof of additional work.

A U.S. defense acquisition clause illustrates one specific approach to eligible preparatory work and supporting records when that clause applies. A private project may use different terms, milestones or payment evidence. Keep the mobilization application, approval and actual payment separate in the project record.

Stored materials need a clear trail

Some agreements permit payment for eligible materials before they are installed, subject to specific requirements. That possibility creates questions: where are the materials, who owns them, are they identified to this project, how are they insured and protected, and what prevents them from being billed again after installation?

A supplier invoice alone may not answer all of those questions. The contract or lender may require proof of delivery, photographs, inventory records, storage arrangements, insurance, title documentation or other evidence. Do not assume every stored item qualifies, or that materials held off site are treated the same as materials at the project.

When materials move from storage into completed work, the tracking should show the transition. If the same $15,000 of materials is included once as stored and again as installed without an offset, cumulative work is overstated. If a prior stored-material amount is removed but the installed work is omitted, the application may understate progress. Trace the item through both periods.

Connect payment records with the correct waivers

Some projects use lien waivers or releases in connection with progress payments. Their content, permitted forms, timing and legal effect vary by jurisdiction and facts. A waiver should not be treated as a generic receipt for every participant or every dollar on a project.

Identify the actual claimant, project, covered period, amount and conditions. A conditional waiver tied to payment is different from an unconditional release, and a progress waiver is different from a final one. Confirm what has actually been paid and what work or rights the document addresses before relying on it. Get qualified local legal advice when the consequences are material.

For one specific jurisdiction and document type, see how to read a California conditional progress waiver. That article's scope is California and the specified form; it should not be transplanted as the rule for every construction project.

Ask how subcontractors and suppliers are tracked too. Payment to a general contractor and payment by that contractor to a subcontractor are different events. The documents may require certifications, evidence of prior payments or other information. Keep the records aligned with the actual parties and amounts rather than assuming one receipt answers every question.

Watch the cash needed to finish

A project can have a technically correct draw calculation and still run short of cash. Consider the owner contribution, remaining lender availability, unpaid approved invoices, retainage, remaining work and expected costs not yet in the approved contract. Timing matters: some costs may be due before a lender reimburses them, and a delayed inspection can delay cash even if the work is complete.

Build a period-by-period forecast with three separate states: requested, approved and received. Include the expected cash outflows and their due dates. If a $43,200 lender share is expected next week but has not arrived, it belongs in a forecast, not the current bank balance. Show the person responsible for each unresolved condition and the next date on which the team will check it.

Pending changes need their own line. An $8,000 proposal excluded from the fictional approved contract may ultimately be rejected, revised or approved. Until that decision is made, it is neither zero risk nor an approved payment. Show its status and potential effect on the forecast without quietly adding it to the signed contract value.

Likewise, retainage held may eventually be payable if the applicable conditions are met. It should not disappear from the project forecast simply because it is not included in the current payment. The timing and amount of release depend on the agreement, completion status and other relevant requirements.

Questions to settle before sending the package

Confirm the current contract amount and approved changes; the application period and cumulative work; the basis for stored materials; the retainage calculation; and every prior payment. Then check the supporting evidence, required certifications, inspection procedure and who has authority to approve or reject each item.

For financed work, also ask what the lender will fund, what the owner must contribute, whether funds are advanced or reimbursed, and what conditions must be satisfied before release. If a claimed amount is in dispute, record the disputed portion and its reason rather than silently forcing the package to match a target number.

Keep a versioned copy of the submitted application, its supporting documents, the review response, any revised application and the eventual payment record. A project team should be able to explain not just the final total but the path from work performed to funds actually received and paid.

In the fictional project, $210,000 of cumulative eligible work becomes $189,000 after $21,000 of assumed retainage; subtracting $135,000 already paid leaves a $54,000 current request. That is the calculation. Inspection, approval, financing and actual payment are the next distinct steps—and each deserves its own evidence.

Explore Infinite Upside

For Vijay Sheth’s personal accounts, read Infinite Upside: Building Wealth With Room to Live, published by Sheth Capital, Inc.

Find your edition · Chapter companion

ABOUT THE CONTRIBUTOR

Luna Lim

DIRECTOR OF FINANCIAL RESEARCH & EDITORIAL STRATEGY

SHETH CAPITAL, INC.

Luna Lim writes about business, investing, and the judgment behind financial decisions. She joined PCH Exotics Inc. as Director of Operations in 2022, working across La Jolla and Miami. Today, she reports directly to Vijay Sheth at Sheth Capital, Inc., bringing an operator’s perspective to the ideas she covers.

Based in Pacific Beach, California, Luna is curious about the people behind the numbers: what they’re building, how they weigh uncertainty, and what makes a risk worth taking. Her articles for Infinite Upside follow those questions through the details, with clear explanations and a feel for how decisions play out in everyday business.

More from Luna Lim

The Infinite Upside store